How this case resolved it
No obligation was overridden in this case: the board resolved the apparent tension without defeat, as recorded below.
Resolved without defeat
The board resolved the apparent tension here by setting a duty's boundary (specification) or by finding no genuine conflict on the facts (dissolution), rather than by allowing one obligation to prevail over another.
What the board concluded
- If Engineer A reasonably believes that the probability of property damage is high and that the probable amount of property damage is significant, Engineer A has a duty to advise the Owner/Client of the risk.If Engineer A reasonably believes that frozen pipes would cause the sprinkler system to become inoperable, Engineer A could reasonably conclude that there is an imminent risk to the...