2"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source."
"Engineer A provides construction services in the community of City B and is a licensed professional engineer in State C where City B is located."
- Provides professional advice and recommendations to an owner rather than performing design or construction under contract
- Advisory standing precedes any contractual engagement on the project
- Professional Engineer license
- Experience with the project delivery methods under consideration
- Objectivity
- Honesty
- Competence
Field classification (triples vs literals)
textReferencescontent: City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.; Engineer A provides construction services in the community of City B and is a licensed professional engineer in State C where City B is located.roleCategorycontent: provider_clientroleKindcontent: professionaldistinguishingFeaturescontent: Provides professional advice and recommendations to an owner rather than performing design or construction under contract; Advisory standing precedes any contractual engagement on the projectprofessionalScopecontent: Advising a public owner on the selection of project delivery methods and related procurement considerations for an engineering projecttypicalQualificationscontent: Professional Engineer license; Experience with the project delivery methods under considerationassociatedVirtuescontent: Objectivity; Honesty; Competenceconfidenceassessment: 0.9
"Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities."
Field classification (triples vs literals)
textReferencescontent: Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities.roleKindcontent: participantdistinguishingFeaturescontent: Owns the wastewater system improvements project and selects the project delivery methodconfidenceassessment: 0.92
Roles Individuals
3Engineer A Consultant Engineer
Consultant Engineer Role"Engineer A provides construction services in the community of City B and is a licensed professional engineer in State C where City B is located."
"Engineer A currently has no contractual relationship with City B."
"Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options."
"Engineer A recommended Progressive Design Build."
"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a ..."
Field classification (triples vs literals)
actor: Engineer Aattributes: {'contractual_status': 'currently has no contractual relationship with City B', 'firm_experience': 'firm has experience with Progressive-Design-Build projects and references from past projects', 'qualified_delivery_methods': 'Progressive-Design-Build and Construction-Manager-at-Risk'}relationships: {'type': 'hasClient', 'target': 'City B', 'quote': 'City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.'}
textReferencescontent: Engineer A provides construction services in the community of City B and is a licensed professional engineer in State C where City B is located.; Engineer A currently has no contractual relationship with City B.; Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.; Engineer A recommended Progressive Design Build.roleClasscontent: Consultant Engineer RoleroleCategorycontent: provider_clientroleKindcontent: professionallicensecontent: Licensed professional engineer in State Cspecialtycontent: Construction servicestechnicalBackgroundcontent: Qualified to provide construction services under Progressive-Design-Build and Construction-Manager-at-Risk delivery methodsadditionalRelationshipscontent: {'type': 'asked for recommendation by', 'target': 'City Administrator', 'quote': 'City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.'}caseInvolvementcontent: Asked by City B's City Administrator for a recommendation on project delivery methods for a wastewater system improvements project. Prepared a summary memo identifying only Design-Bid-Build and Progressive-Design-Build as viable options, recommended Progressive Design Build, and provided a summary of the firm's Progressive-Design-Build experience and references from past projects.confidenceassessment: 0.92
City Administrator Municipal Official
Municipal Official Role"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source."
"City Administrator is not a licensed professional engineer."
"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a ..."
Field classification (triples vs literals)
actor: City Administratorattributes: {'licensure_status': 'not a licensed professional engineer'}relationships: {'type': 'employedBy', 'target': 'City B', 'quote': 'City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.'}
textReferencescontent: City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.; City Administrator is not a licensed professional engineer.roleClasscontent: Municipal Official RoleroleKindcontent: participantemployercontent: City BtechnicalBackgroundcontent: Not a licensed professional engineeradditionalRelationshipscontent: {'type': 'requested recommendation from', 'target': 'Engineer A', 'quote': 'City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.'}caseInvolvementcontent: Asked Engineer A for a recommendation on project delivery methods for City B's upcoming wastewater system improvements project and received Engineer A's summary memo and recommendation.confidenceassessment: 0.88
City B Owner
Owner Role"Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities."
"City B is a large metropolitan area and all forms of contracting are available."
Field classification (triples vs literals)
actor: City Battributes: {'municipality_type': 'large metropolitan area where all forms of contracting are available', 'project': 'upcoming wastewater system improvements project using a specific funding source', 'funding_constraint': 'if Construction Manager at Risk is selected, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities'}
textReferencescontent: Additionally, if Construction Manager at Risk is selected by the owner, City B, the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities.; City B is a large metropolitan area and all forms of contracting are available.roleClasscontent: Owner RoleroleKindcontent: participantcaseInvolvementcontent: Owner of the upcoming wastewater system improvements project. As owner it selects the project delivery method from the four methods approved under the proposed funding source, subject to the funding agency requirement that the Construction Manager at Risk firm and the Engineer of Record be two distinct entities.confidenceassessment: 0.9
S States
States Classes
5"Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build."
"the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities"
Field classification (triples vs literals)
textReferencescontent: Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build.; the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entitiesstateCategorycontent: regulatorypersistenceTypecontent: inertialprincipleTransformationcontent: The compliance principle becomes a concrete bound on which delivery methods may be recommended and on who may serve in each capacity under the selected method.confidenceassessment: 0.9
activationConditions: A funding source with attached delivery-method requirements is proposed for the projectterminationConditions: The funding source is abandoned or its requirements are amendedobligationActivation: Obligation to advise the client consistently with the funding source's approved delivery methods and conditionsactionConstraints: Constraint that under Construction Manager at Risk the CMAR firm and the Engineer of Record must be two distinct entities
"Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options."
Field classification (triples vs literals)
textReferencescontent: Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.stateCategorycontent: disclosurepersistenceTypecontent: inertialprincipleTransformationcontent: The honesty and objectivity principle becomes a concrete requirement to present all four approved delivery methods to the client rather than only the two identified in the memo.confidenceassessment: 0.93
activationConditions: A professional delivers advice or a work product that presents only a subset of the available options or material informationterminationConditions: The professional supplements or corrects the advice to disclose all approved optionsobligationActivation: Obligation to be objective and truthful and to include all relevant and pertinent information in professional reports and adviceactionConstraints: Prohibition on misleading omissions in advisory work product
"Engineer A currently has no contractual relationship with City B."
Field classification (triples vs literals)
textReferencescontent: Engineer A currently has no contractual relationship with City B.stateCategorycontent: regulatorypersistenceTypecontent: inertialprincipleTransformationcontent: The absence of an existing engagement frames Engineer A's advice as pre-retention conduct, so the duties in force are those governing honest dealings with a prospective client rather than duties under a contract.confidenceassessment: 0.85
activationConditions: The professional has not been retained and holds no contract with the partyterminationConditions: The party retains the professional under a contract
"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source."
"City Administrator is not a licensed professional engineer."
Field classification (triples vs literals)
textReferencescontent: City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.; City Administrator is not a licensed professional engineer.stateCategorycontent: epistemicpersistenceTypecontent: inertialprincipleTransformationcontent: The client's dependence on Engineer A's judgment transforms the objectivity principle into a concrete duty to present the delivery options completely and without bias.confidenceassessment: 0.82
activationConditions: A non-engineer decision maker asks a professional engineer for a recommendation on a technical procurement questionterminationConditions: The client obtains independent engineering advice or the decision is madeobligationActivation: Obligation to provide complete and objective advice to a client who depends on the engineer's judgment
"Engineer A recommended Progressive Design Build."
"Engineer A recommended Progressive Design Build. Accompanying the recommendation, Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past..."
Field classification (triples vs literals)
textReferencescontent: Engineer A recommended Progressive Design Build.; Engineer A recommended Progressive Design Build. Accompanying the recommendation, Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past projectsstateCategorycontent: conflict_of_interestpersistenceTypecontent: inertialprincipleTransformationcontent: The faithful agent principle becomes a concrete requirement that Engineer A disclose the firm's interest in performing construction services under the recommended delivery method.confidenceassessment: 0.88
activationConditions: A professional is asked to advise a party on a decision from which the professional's own firm stands to gain workterminationConditions: The professional discloses the interest, withdraws from the advisory role, or forgoes the prospective workobligationActivation: Obligation to disclose known or potential conflicts of interest to the clientactionConstraints: Restriction on rendering advice biased toward the professional's own prospective engagement
States Individuals
5Self Interested Delivery Recommendation
Conflict Of Interest State"Engineer A recommended Progressive Design Build."
"Engineer A recommended Progressive Design Build. Accompanying the recommendation, Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past..."
- City B
- City B City Administrator
- Engineer A
Field classification (triples vs literals)
textReferencescontent: Engineer A recommended Progressive Design Build.; Engineer A recommended Progressive Design Build. Accompanying the recommendation, Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past projectsstateClasscontent: Conflict Of Interest Statesubjectcontent: Engineer A, advising City B on delivery methods while positioned to provide construction services under the recommended Progressive-Design-Build methodactivePeriodcontent: From the City Administrator's request for a recommendation through the delivery of the recommendation and any subsequent pursuit of the worktriggeringEventcontent: City B's City Administrator asks Engineer A, a provider of construction services, for a recommendation on project delivery methodsterminatedBycontent: Engineer A discloses the firm's interest, withdraws from the advisory role, or forgoes construction work on the projectaffectedPartiescontent: City B; City B City Administrator; Engineer Aconfidenceassessment: 0.88urgencyLevelassessment: high
Omitted Delivery Options Memo
Selective Reporting State"Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options."
- City B
- City B City Administrator
Field classification (triples vs literals)
textReferencescontent: Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.stateClasscontent: Selective Reporting Statesubjectcontent: Engineer A's summary memo to the City B AdministratoractivePeriodcontent: From delivery of the summary memo until the omitted delivery methods are disclosed or the city decidestriggeringEventcontent: Engineer A prepares and submits the summary memo identifying only Design-Bid-Build and Progressive-Design-Build as viable optionsterminatedBycontent: Engineer A supplements the memo to present all four approved delivery methods, or City B otherwise learns of the omitted optionsaffectedPartiescontent: City B; City B City Administratorconfidenceassessment: 0.93urgencyLevelassessment: high
Funding Agency Entity Separation Requirement
Regulatory Requirement State"Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build."
"the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities"
- City B
- Engineer A
Field classification (triples vs literals)
textReferencescontent: Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build.; the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entitiesstateClasscontent: Regulatory Requirement Statesubjectcontent: City B's wastewater system improvements project under the proposed funding sourceactivePeriodcontent: While the proposed funding source and its requirements govern the projecttriggeringEventcontent: City B proposes to use the specific funding source with its four approved delivery methods and entity-separation conditionterminatedBycontent: The funding source is abandoned or the funding agency's requirements are amendedaffectedPartiescontent: City B; Engineer Aconfidenceassessment: 0.9urgencyLevelassessment: medium
No Contract With City B
Retention Commitment Absence State"Engineer A currently has no contractual relationship with City B."
- Engineer A
- City B
Field classification (triples vs literals)
textReferencescontent: Engineer A currently has no contractual relationship with City B.stateClasscontent: Retention Commitment Absence Statesubjectcontent: Engineer A with respect to City BactivePeriodcontent: During the period in which the recommendation is requested and providedtriggeringEventcontent: The situation obtains at the outset of the case, before the City Administrator's requestterminatedBycontent: City B retains Engineer A under a contract, if that occursaffectedPartiescontent: Engineer A; City Bconfidenceassessment: 0.9urgencyLevelassessment: low
Non Engineer Administrator Reliance
Client Reliance State"City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source."
"City Administrator is not a licensed professional engineer."
- City B City Administrator
- City B
Field classification (triples vs literals)
textReferencescontent: City B’s City Administrator asked Engineer A for a recommendation on project delivery methods for their upcoming wastewater system improvements project using a specific funding source.; City Administrator is not a licensed professional engineer.stateClasscontent: Client Reliance Statesubjectcontent: City B's City Administrator, who is not a licensed professional engineer and seeks Engineer A's recommendationactivePeriodcontent: From the request for a recommendation until City B selects a project delivery methodtriggeringEventcontent: The City Administrator asks Engineer A for a recommendation on project delivery methods for the wastewater projectterminatedBycontent: City B makes its delivery method selection or obtains independent engineering adviceaffectedPartiescontent: City B City Administrator; City Bconfidenceassessment: 0.82urgencyLevelassessment: medium
Rs Resources
Resources Classes
2"Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build."
"the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entities"
Field classification (triples vs literals)
textReferencescontent: Under the proposed funding source, there are four approved project delivery methods: Design-Bid-Build, Construction-Management-at-Risk, Fixed-Price-Design-Build, and Progressive-Design-Build.; the funding agency requires the Construction Manager at Risk firm and the Engineer of Record be two distinct entitiesresourceCategorycontent: legal_resourceconfidenceassessment: 0.85
"Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options."
"Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past projects"
Field classification (triples vs literals)
textReferencescontent: Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.; Engineer A provided a summary of the firm’s experience with Progressive-Design-Build projects and references from past projectsresourceCategorycontent: reference_materialconfidenceassessment: 0.8
Resources Individuals
1Engineer A Summary Memo
Reference Material"Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options."
Field classification (triples vs literals)
usedBy: City B Administrator
textReferencescontent: Engineer A prepared a summary memo to City B Administrator and only identified Design-Bid-Build and Progressive-Design-Build as viable project delivery options.resourceClasscontent: Reference Materialtopiccontent: recommended project delivery methods for the wastewater system improvements projectconfidenceassessment: 0.8