PASS 1: Contextual Framework Facts Section
Case 15: Independence of Peer Reviewer
R Roles
S States
Rs Resources
Extracted Ontology Entities
R Roles
Roles Classes
0Roles Individuals
3Engineer A Design Engineer
Design Engineer Role"several significant design errors are discovered in the plans and design of Engineer A"
"Engineer A objects and refused to consent to the peer review"
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower"
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
Field classification (triples vs literals)
actor: Engineer Aattributes: {'design_status': 'significant design errors discovered in plans and design during construction of first tower'}relationships: {'type': 'hasClient', 'target': 'Owner', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower'}; {'type': 'workReviewedBy', 'target': 'Engineer B', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B'}
textReferencescontent: several significant design errors are discovered in the plans and design of Engineer A; Engineer A objects and refused to consent to the peer reviewroleClasscontent: Design Engineer RoleroleCategorycontent: provider_clientroleKindcontent: professionaladditionalRelationshipscontent: {'type': 'refused consent to peer review by', 'target': 'Engineer B', 'quote': 'Engineer A objects and refused to consent to the peer review'}caseInvolvementcontent: Prepared the plans and design for the two mirror-image towers; significant design errors were discovered in the plans during construction of the first tower, and when notified of the peer review of the second tower design, Engineer A objected and refused to consent.confidenceassessment: 0.92
Engineer B Peer Reviewer
Engineer Role"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
"Engineer B objects to conducting the peer review without advising Engineer A"
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
Field classification (triples vs literals)
actor: Engineer Battributes: {'engagement': "retained by Owner to conduct a peer review of Engineer A's plans and design for the second tower"}relationships: {'type': 'hasClient', 'target': 'Owner', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B'}; {'type': 'reviewsWorkOf', 'target': 'Engineer A', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B'}
textReferencescontent: Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B; Engineer B objects to conducting the peer review without advising Engineer AroleClasscontent: Engineer RoleroleCategorycontent: provider_clientroleKindcontent: professionaladditionalRelationshipscontent: {'type': 'objected to concealment instruction from', 'target': 'Owner', 'quote': 'Engineer B objects to conducting the peer review without advising Engineer A'}caseInvolvementcontent: Retained by Owner to peer review Engineer A's plans and design for the second tower; instructed by Owner to conduct the review without letting Engineer A know, Engineer B objected to conducting the peer review without advising Engineer A.confidenceassessment: 0.9
Owner Developer
Owner Role"wner is developing a site with two mirror-image towers to be built two years apart"
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
"When Owner reluctantly consents to notifying Engineer A"
- {'type': 'retains', 'target': 'Engineer B', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B'}
- {'type': 'instructs', 'target': 'Engineer B', 'quote': 'Owner instructs Engineer B to conduct the peer review without letting Engineer A know'}
- {'type': 'reluctantly consents to notifying', 'target': 'Engineer A', 'quote': 'When Owner reluctantly consents to notifying Engineer A'}
Field classification (triples vs literals)
actor: Ownerattributes: {'project': 'developing a site with two mirror-image towers to be built two years apart'}
textReferencescontent: wner is developing a site with two mirror-image towers to be built two years apart; Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B; When Owner reluctantly consents to notifying Engineer AroleClasscontent: Owner RoleroleKindcontent: participantadditionalRelationshipscontent: {'type': 'retains', 'target': 'Engineer B', 'quote': 'Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B'}; {'type': 'instructs', 'target': 'Engineer B', 'quote': 'Owner instructs Engineer B to conduct the peer review without letting Engineer A know'}; {'type': 'reluctantly consents to notifying', 'target': 'Engineer A', 'quote': 'When Owner reluctantly consents to notifying Engineer A'}caseInvolvementcontent: Developing the site with two mirror-image towers; after design errors were discovered in Engineer A's plans, decided to obtain a peer review of the second tower design, retained Engineer B, instructed Engineer B to conduct the review without letting Engineer A know, and later reluctantly consented to notifying Engineer A.confidenceassessment: 0.9
S States
States Classes
5"several significant design errors are discovered in the plans and design of Engineer A"
Field classification (triples vs literals)
textReferencescontent: several significant design errors are discovered in the plans and design of Engineer AstateCategorycontent: riskpersistenceTypecontent: inertialprincipleTransformationcontent: The deficiency of the delivered plans makes independent verification of the design for the second tower a concrete concern for the Owner.confidenceassessment: 0.92
activationConditions: Significant design errors are discovered in delivered plans and design during constructionterminationConditions: The design errors are corrected in the plans for the remaining workobligationActivation: Peer Review Obligation
"Owner instructs Engineer B to conduct the peer review without letting Engineer A know"
"Engineer B objects to conducting the peer review without advising Engineer A"
Field classification (triples vs literals)
textReferencescontent: Owner instructs Engineer B to conduct the peer review without letting Engineer A know; Engineer B objects to conducting the peer review without advising Engineer AstateCategorycontent: conflict_of_interestpersistenceTypecontent: inertialprincipleTransformationcontent: The covert instruction turns the general duty of fair dealing toward a fellow engineer into a concrete question of whether Engineer B may proceed without advising Engineer A.confidenceassessment: 0.88
activationConditions: Client instructs the reviewing engineer to conduct a peer review without the knowledge of the engineer whose work is reviewedterminationConditions: Client consents to notifying the engineer whose work is under reviewobligationActivation: Notification Obligation to the Reviewed Engineer
"Owner reluctantly consents to notifying Engineer A"
Field classification (triples vs literals)
textReferencescontent: Owner reluctantly consents to notifying Engineer AstateCategorycontent: epistemicpersistenceTypecontent: inertialprincipleTransformationcontent: Once Engineer A knows of the review, the notice condition attached to reviewing another engineer's work is satisfied and the dispute shifts to consent.confidenceassessment: 0.85
activationConditions: The engineer whose work is under review is notified of the reviewing engineer's retention
"Engineer A objects and refused to consent to the peer review"
Field classification (triples vs literals)
textReferencescontent: Engineer A objects and refused to consent to the peer reviewstateCategorycontent: disclosurepersistenceTypecontent: inertialprincipleTransformationcontent: Engineer A's refusal of consent makes the propriety of proceeding with the peer review over the objection the concrete question the parties face.confidenceassessment: 0.87
activationConditions: The engineer whose work is under review objects and refuses to consent to the peer reviewterminationConditions: The engineer whose work is under review grants consent to the peer review
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
Field classification (triples vs literals)
textReferencescontent: Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer BstateCategorycontent: regulatorypersistenceTypecontent: inertialprincipleTransformationcontent: The retention places Engineer B under the duties owed a retaining client while the peer review engagement is in force.confidenceassessment: 0.9
activationConditions: Client retains the professional for defined servicesterminationConditions: The engagement is completed or terminated by the clientobligationActivation: Faithful Agent Obligation to the Client
States Individuals
5"As the first tower is built, several significant design errors are discovered in the plans and design of Engineer A"
- Owner
- Engineer A
Field classification (triples vs literals)
textReferencescontent: As the first tower is built, several significant design errors are discovered in the plans and design of Engineer AstateClasscontent: Incomplete Submission Statesubjectcontent: The plans and design of Engineer A for the two mirror-image towersactivePeriodcontent: From delivery of the plans, with the errors discovered as the first tower is built, until the errors are correctedtriggeringEventcontent: Several significant design errors are discovered in the plans and design of Engineer A as the first tower is builtterminatedBycontent: Correction of the design errors in the plans for the second toweraffectedPartiescontent: Owner; Engineer Aconfidenceassessment: 0.92urgencyLevelassessment: high
"Owner instructs Engineer B to conduct the peer review without letting Engineer A know"
- Engineer B
- Engineer A
- Owner
Field classification (triples vs literals)
textReferencescontent: Owner instructs Engineer B to conduct the peer review without letting Engineer A knowstateClasscontent: Conflict Of Interest Statesubjectcontent: Engineer B, retained by the Owner for the peer reviewactivePeriodcontent: From the Owner's instruction to conduct the review secretly until the Owner reluctantly consents to notifying Engineer AtriggeringEventcontent: Owner instructs Engineer B to conduct the peer review without letting Engineer A knowterminatedBycontent: Owner reluctantly consents to notifying Engineer AaffectedPartiescontent: Engineer B; Engineer A; Ownerconfidenceassessment: 0.88urgencyLevelassessment: medium
"When Owner reluctantly consents to notifying Engineer A, Engineer A objects and refused to consent to the peer review"
- Engineer A
- Engineer B
- Owner
Field classification (triples vs literals)
textReferencescontent: When Owner reluctantly consents to notifying Engineer A, Engineer A objects and refused to consent to the peer reviewstateClasscontent: Peer Review Awareness Statesubjectcontent: Engineer A, the engineer whose plans and design are under peer reviewactivePeriodcontent: From the notification of Engineer A onwardtriggeringEventcontent: Owner reluctantly consents to notifying Engineer A and Engineer A is advised of the peer reviewaffectedPartiescontent: Engineer A; Engineer B; Ownerconfidenceassessment: 0.85urgencyLevelassessment: low
"Engineer A objects and refused to consent to the peer review"
- Owner
- Engineer B
- Engineer A
Field classification (triples vs literals)
textReferencescontent: Engineer A objects and refused to consent to the peer reviewstateClasscontent: Peer Review Consent Statesubjectcontent: Engineer A's consent to the peer review of his plans and designactivePeriodcontent: From Engineer A's objection and refusal onwardtriggeringEventcontent: Engineer A objects and refused to consent to the peer review after being notifiedterminatedBycontent: Engineer A granting consent to the peer review, if that occursaffectedPartiescontent: Owner; Engineer B; Engineer Aconfidenceassessment: 0.9urgencyLevelassessment: medium
"Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer B"
- Engineer B
- Owner
- Engineer A
Field classification (triples vs literals)
textReferencescontent: Owner decides to obtain a peer review of the plans and design of Engineer A for the second tower and retains Engineer BstateClasscontent: Active Engagement Statesubjectcontent: Engineer B, retained by the Owner to peer review the plans and design of Engineer A for the second toweractivePeriodcontent: From the Owner's retention of Engineer B while the peer review engagement remains in forcetriggeringEventcontent: Owner retains Engineer B to conduct the peer review for the second towerterminatedBycontent: Completion or termination of the peer review engagementaffectedPartiescontent: Engineer B; Owner; Engineer Aconfidenceassessment: 0.9urgencyLevelassessment: low
Rs Resources
The extraction did not find any resources to add. This typically means the case text doesn't contain relevant resources for this section, or extraction hasn't been run yet.