PASS 3: Temporal Dynamics
Case 85: Incomplete Plans and Specifications – Engineer, Government, and Contractor Responsibilities
Timeline Overview
OWL-Time Temporal Structure 12 relations time: = w3.org/2006/time
Extracted Actions (6)
Volitional professional decisions with intentions and ethical contextDescription: Engineer A's firm decided to respond to the local public agency's RFP for dam design, submitting an impressive brochure and completing a personal interview, thereby implicitly committing to deliver a complete and competent design within the project's stated time parameters.
Temporal Marker: Pre-contract phase, prior to contract award instant
Fluent Transitions:
- Design Contract Obligation Active
- Client Reliance on Engineer A
Mental State: deliberate
Intended Outcome: Win the design contract for the dam project
Foreseen Unintended Effects:
- Commitment to deliverables within time parameters that may prove difficult to meet
Obligation Engagement:
- Obligation to perform services within area of competence by representing the firm as capable
Guided By Principles:
- Professional competence
- Honest representation to client
Required Capabilities:
Field classification (triples vs literals)
fulfillsObligation: Obligation to perform services within area of competence by representing the firm as capableguidedByPrinciple: Professional competence; Honest representation to clientinitiates: Design Contract Obligation Active; Client Reliance on Engineer A
descriptioncontent: Engineer A's firm decided to respond to the local public agency's RFP for dam design, submitting an impressive brochure and completing a personal interview, thereby implicitly committing to deliver a complete and competent design within the project's stated time parameters.hasAgentcontent: Engineer AtemporalMarkercontent: Pre-contract phase, prior to contract awardeventRoleContextcontent: Design Engineer, firm principalhasMentalStatecontent: deliberateintendedOutcomecontent: Win the design contract for the dam projectforeseenUnintendedEffectscontent: Commitment to deliverables within time parameters that may prove difficult to meettemporalExtentcontent: instanttemporalSequencecontent: 2withinCompetenceassessment: True
requiresCapability: Dam design expertise; Project scoping and scheduling judgment
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_RFP_Response_Submission",
"@type": "proeth:Action",
"proeth:description": "Engineer A\u0027s firm decided to respond to the local public agency\u0027s RFP for dam design, submitting an impressive brochure and completing a personal interview, thereby implicitly committing to deliver a complete and competent design within the project\u0027s stated time parameters.",
"proeth:eventRoleContext": "Design Engineer, firm principal",
"proeth:foreseenUnintendedEffects": [
"Commitment to deliverables within time parameters that may prove difficult to meet"
],
"proeth:fulfillsObligation": [
"Obligation to perform services within area of competence by representing the firm as capable"
],
"proeth:guidedByPrinciple": [
"Professional competence",
"Honest representation to client"
],
"proeth:hasAgent": "Engineer A",
"proeth:hasMentalState": "deliberate",
"proeth:initiates": [
"Design Contract Obligation Active",
"Client Reliance on Engineer A"
],
"proeth:intendedOutcome": "Win the design contract for the dam project",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Dam design expertise",
"Project scoping and scheduling judgment"
],
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Pre-contract phase, prior to contract award",
"proeth:temporalSequence": 2,
"proeth:violatesObligation": [],
"proeth:withinCompetence": true,
"rdfs:label": "RFP Response Submission"
}
Description: Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified deadline, citing time pressure as justification, rather than requesting an extension or otherwise seeking relief from the schedule constraint.
Temporal Marker: Design phase, at the deadline for deliverable submission instant
Fluent Transitions:
- Incomplete Documents in Circulation
- Public Safety Risk Latent
- Unjustified Expenditure of Public Funds Risk
Mental State: deliberate
Intended Outcome: Meet the contractual delivery deadline and avoid conflict with the client over schedule
Foreseen Unintended Effects:
- Submission of documents insufficient to support construction
- Risk of increased project costs
Obligation Engagement:
- Obligation to provide complete design drawings and specifications
- Obligation to avoid deceptive acts
- Obligation to perform services within area of competence
Guided By Principles:
- Completeness of professional deliverables
- Honest representation to client
- Public fund stewardship
Required Capabilities:
Field classification (triples vs literals)
violatesObligation: Obligation to provide complete design drawings and specifications; Obligation to avoid deceptive acts; Obligation to perform services within area of competenceguidedByPrinciple: Completeness of professional deliverables; Honest representation to client; Public fund stewardshipinitiates: Incomplete Documents in Circulation; Public Safety Risk Latent; Unjustified Expenditure of Public Funds Risk
descriptioncontent: Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified deadline, citing time pressure as justification, rather than requesting an extension or otherwise seeking relief from the schedule constraint.hasAgentcontent: Engineer AtemporalMarkercontent: Design phase, at the deadline for deliverable submissioneventRoleContextcontent: Design EngineerhasMentalStatecontent: deliberateintendedOutcomecontent: Meet the contractual delivery deadline and avoid conflict with the client over scheduleforeseenUnintendedEffectscontent: Submission of documents insufficient to support construction; Risk of increased project coststemporalExtentcontent: instanttemporalSequencecontent: 5withinCompetenceassessment: False
requiresCapability: Dam design to completion; Scheduling judgment to flag infeasible deadlines; Conformance with applicable engineering standards
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_Incomplete_Work_Submission",
"@type": "proeth:Action",
"proeth:description": "Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified deadline, citing time pressure as justification, rather than requesting an extension or otherwise seeking relief from the schedule constraint.",
"proeth:eventRoleContext": "Design Engineer",
"proeth:foreseenUnintendedEffects": [
"Submission of documents insufficient to support construction",
"Risk of increased project costs"
],
"proeth:fulfillsObligation": [],
"proeth:guidedByPrinciple": [
"Completeness of professional deliverables",
"Honest representation to client",
"Public fund stewardship"
],
"proeth:hasAgent": "Engineer A",
"proeth:hasMentalState": "deliberate",
"proeth:initiates": [
"Incomplete Documents in Circulation",
"Public Safety Risk Latent",
"Unjustified Expenditure of Public Funds Risk"
],
"proeth:intendedOutcome": "Meet the contractual delivery deadline and avoid conflict with the client over schedule",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Dam design to completion",
"Scheduling judgment to flag infeasible deadlines",
"Conformance with applicable engineering standards"
],
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Design phase, at the deadline for deliverable submission",
"proeth:temporalSequence": 5,
"proeth:violatesObligation": [
"Obligation to provide complete design drawings and specifications",
"Obligation to avoid deceptive acts",
"Obligation to perform services within area of competence"
],
"proeth:withinCompetence": false,
"rdfs:label": "Incomplete Work Submission"
}
Description: Engineer A decided not to inform the local public agency, the federal funding agency, or any other stakeholder that the submitted drawings and specifications were incomplete, privately rationalizing that federal funds would cover any resulting cost overruns.
Temporal Marker: Design phase, concurrent with and following submission of incomplete documents interval
Fluent Transitions:
- Stakeholder Uninformed of Deficiencies
- Misrepresentation of Deliverable Completeness
Mental State: deliberate
Intended Outcome: Avoid accountability for incomplete work and preserve the client relationship by assuming federal funds would absorb additional costs
Foreseen Unintended Effects:
- Client and federal agency proceed without knowledge of deficiencies
- Increased risk of cost overruns charged to federal funds
- Contractor awarded work based on deficient documents
Obligation Engagement:
- Obligation to avoid deceptive acts
- Obligation to provide complete design drawings and specifications
- Obligation of honest disclosure to client and funding agency
- Public fund stewardship
Guided By Principles:
- Transparency with clients and public agencies
- Honest representation to client
- Public fund stewardship
Required Capabilities:
Field classification (triples vs literals)
violatesObligation: Obligation to avoid deceptive acts; Obligation to provide complete design drawings and specifications; Obligation of honest disclosure to client and funding agency; Public fund stewardshipguidedByPrinciple: Transparency with clients and public agencies; Honest representation to client; Public fund stewardshipinitiates: Stakeholder Uninformed of Deficiencies; Misrepresentation of Deliverable Completeness
descriptioncontent: Engineer A decided not to inform the local public agency, the federal funding agency, or any other stakeholder that the submitted drawings and specifications were incomplete, privately rationalizing that federal funds would cover any resulting cost overruns.hasAgentcontent: Engineer AtemporalMarkercontent: Design phase, concurrent with and following submission of incomplete documentseventRoleContextcontent: Design EngineerhasMentalStatecontent: deliberateintendedOutcomecontent: Avoid accountability for incomplete work and preserve the client relationship by assuming federal funds would absorb additional costsforeseenUnintendedEffectscontent: Client and federal agency proceed without knowledge of deficiencies; Increased risk of cost overruns charged to federal funds; Contractor awarded work based on deficient documentstemporalExtentcontent: intervaltemporalSequencecontent: 6withinCompetenceassessment: True
requiresCapability: Professional judgment to communicate limitations to client; Ethical obligation to disclose known deficiencies
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_Non-Disclosure_of_Incompleteness",
"@type": "proeth:Action",
"proeth:description": "Engineer A decided not to inform the local public agency, the federal funding agency, or any other stakeholder that the submitted drawings and specifications were incomplete, privately rationalizing that federal funds would cover any resulting cost overruns.",
"proeth:eventRoleContext": "Design Engineer",
"proeth:foreseenUnintendedEffects": [
"Client and federal agency proceed without knowledge of deficiencies",
"Increased risk of cost overruns charged to federal funds",
"Contractor awarded work based on deficient documents"
],
"proeth:fulfillsObligation": [],
"proeth:guidedByPrinciple": [
"Transparency with clients and public agencies",
"Honest representation to client",
"Public fund stewardship"
],
"proeth:hasAgent": "Engineer A",
"proeth:hasMentalState": "deliberate",
"proeth:initiates": [
"Stakeholder Uninformed of Deficiencies",
"Misrepresentation of Deliverable Completeness"
],
"proeth:intendedOutcome": "Avoid accountability for incomplete work and preserve the client relationship by assuming federal funds would absorb additional costs",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Professional judgment to communicate limitations to client",
"Ethical obligation to disclose known deficiencies"
],
"proeth:temporalExtent": "interval",
"proeth:temporalMarker": "Design phase, concurrent with and following submission of incomplete documents",
"proeth:temporalSequence": 6,
"proeth:violatesObligation": [
"Obligation to avoid deceptive acts",
"Obligation to provide complete design drawings and specifications",
"Obligation of honest disclosure to client and funding agency",
"Public fund stewardship"
],
"proeth:withinCompetence": true,
"rdfs:label": "Non-Disclosure of Incompleteness"
}
Description: Engineer B, acting on behalf of the federal funding agency's engineering staff, decided to approve Engineer A's incomplete drawings and specifications without flagging identified or identifiable deficiencies or escalating the review to a more competent reviewer.
Temporal Marker: Review phase, prior to project advertisement for bids instant
Fluent Transitions:
- Federal Approval of Deficient Documents
- Project Cleared for Bidding
- Federal Review Process Active
Mental State: deliberate
Intended Outcome: Complete the federal review and approval process to allow the project to proceed to bidding
Foreseen Unintended Effects:
- Incomplete documents advanced to bidding without correction
- Federal funds committed to a project with deficient design basis
Obligation Engagement:
- Obligation to perform services within area of competence
- Obligation to recognize limits of competency and escalate appropriately
- Public fund stewardship
Guided By Principles:
- Competence in professional review
- Responsible stewardship of federal funds
- Honest representation to client
Required Capabilities:
Field classification (triples vs literals)
violatesObligation: Obligation to perform services within area of competence; Obligation to recognize limits of competency and escalate appropriately; Public fund stewardshipguidedByPrinciple: Competence in professional review; Responsible stewardship of federal funds; Honest representation to clientinitiates: Federal Approval of Deficient Documents; Project Cleared for Biddingterminates: Federal Review Process Active
descriptioncontent: Engineer B, acting on behalf of the federal funding agency's engineering staff, decided to approve Engineer A's incomplete drawings and specifications without flagging identified or identifiable deficiencies or escalating the review to a more competent reviewer.hasAgentcontent: Engineer BtemporalMarkercontent: Review phase, prior to project advertisement for bidseventRoleContextcontent: Federal Agency Engineering Staff ReviewerhasMentalStatecontent: deliberateintendedOutcomecontent: Complete the federal review and approval process to allow the project to proceed to biddingforeseenUnintendedEffectscontent: Incomplete documents advanced to bidding without correction; Federal funds committed to a project with deficient design basistemporalExtentcontent: instanttemporalSequencecontent: 7withinCompetenceassessment: False
requiresCapability: Dam design review expertise; Ability to identify incomplete or non-conforming engineering documents; Judgment to escalate review beyond personal competence
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_Incomplete_Documents_Approval",
"@type": "proeth:Action",
"proeth:description": "Engineer B, acting on behalf of the federal funding agency\u0027s engineering staff, decided to approve Engineer A\u0027s incomplete drawings and specifications without flagging identified or identifiable deficiencies or escalating the review to a more competent reviewer.",
"proeth:eventRoleContext": "Federal Agency Engineering Staff Reviewer",
"proeth:foreseenUnintendedEffects": [
"Incomplete documents advanced to bidding without correction",
"Federal funds committed to a project with deficient design basis"
],
"proeth:fulfillsObligation": [],
"proeth:guidedByPrinciple": [
"Competence in professional review",
"Responsible stewardship of federal funds",
"Honest representation to client"
],
"proeth:hasAgent": "Engineer B",
"proeth:hasMentalState": "deliberate",
"proeth:initiates": [
"Federal Approval of Deficient Documents",
"Project Cleared for Bidding"
],
"proeth:intendedOutcome": "Complete the federal review and approval process to allow the project to proceed to bidding",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Dam design review expertise",
"Ability to identify incomplete or non-conforming engineering documents",
"Judgment to escalate review beyond personal competence"
],
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Review phase, prior to project advertisement for bids",
"proeth:temporalSequence": 7,
"proeth:terminates": [
"Federal Review Process Active"
],
"proeth:violatesObligation": [
"Obligation to perform services within area of competence",
"Obligation to recognize limits of competency and escalate appropriately",
"Public fund stewardship"
],
"proeth:withinCompetence": false,
"rdfs:label": "Incomplete Documents Approval"
}
Description: Engineer C, as owner of Hi-Lo Construction, decided to submit the low bid on the dam project based on documents that, upon review, should have revealed incompleteness and unbuildable elements, without seeking clarification from the owner or Engineer A and without adjusting the bid to reflect the additional work required.
Temporal Marker: Bidding phase, prior to contract award instant
Fluent Transitions:
- Construction Contract Awarded on Deficient Documents
- Contractor Exposed to Unbuildable Conditions
Mental State: deliberate
Intended Outcome: Win the construction contract by submitting the lowest bid
Foreseen Unintended Effects:
- Exposure to cost overruns and constructability problems arising from deficient documents
- Risk of contract performance on an unbuildable design
Obligation Engagement:
- Obligation to perform services within area of competence
- Obligation to make an informed professional judgment before committing to contract performance
Guided By Principles:
- Informed risk assessment before bidding
- Professional competence
- Honest representation to client
Required Capabilities:
Field classification (triples vs literals)
violatesObligation: Obligation to perform services within area of competence; Obligation to make an informed professional judgment before committing to contract performanceguidedByPrinciple: Informed risk assessment before bidding; Professional competence; Honest representation to clientinitiates: Construction Contract Awarded on Deficient Documents; Contractor Exposed to Unbuildable Conditions
descriptioncontent: Engineer C, as owner of Hi-Lo Construction, decided to submit the low bid on the dam project based on documents that, upon review, should have revealed incompleteness and unbuildable elements, without seeking clarification from the owner or Engineer A and without adjusting the bid to reflect the additional work required.hasAgentcontent: Engineer CtemporalMarkercontent: Bidding phase, prior to contract awardeventRoleContextcontent: Owner, Hi-Lo ConstructionhasMentalStatecontent: deliberateintendedOutcomecontent: Win the construction contract by submitting the lowest bidforeseenUnintendedEffectscontent: Exposure to cost overruns and constructability problems arising from deficient documents; Risk of contract performance on an unbuildable designtemporalExtentcontent: instanttemporalSequencecontent: 10withinCompetenceassessment: False
requiresCapability: Construction document review and evaluation; Engineering judgment to identify unbuildable or incomplete design elements; Bid preparation reflecting actual project risks
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_Low_Bid_Submission",
"@type": "proeth:Action",
"proeth:description": "Engineer C, as owner of Hi-Lo Construction, decided to submit the low bid on the dam project based on documents that, upon review, should have revealed incompleteness and unbuildable elements, without seeking clarification from the owner or Engineer A and without adjusting the bid to reflect the additional work required.",
"proeth:eventRoleContext": "Owner, Hi-Lo Construction",
"proeth:foreseenUnintendedEffects": [
"Exposure to cost overruns and constructability problems arising from deficient documents",
"Risk of contract performance on an unbuildable design"
],
"proeth:fulfillsObligation": [],
"proeth:guidedByPrinciple": [
"Informed risk assessment before bidding",
"Professional competence",
"Honest representation to client"
],
"proeth:hasAgent": "Engineer C",
"proeth:hasMentalState": "deliberate",
"proeth:initiates": [
"Construction Contract Awarded on Deficient Documents",
"Contractor Exposed to Unbuildable Conditions"
],
"proeth:intendedOutcome": "Win the construction contract by submitting the lowest bid",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Construction document review and evaluation",
"Engineering judgment to identify unbuildable or incomplete design elements",
"Bid preparation reflecting actual project risks"
],
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Bidding phase, prior to contract award",
"proeth:temporalSequence": 10,
"proeth:violatesObligation": [
"Obligation to perform services within area of competence",
"Obligation to make an informed professional judgment before committing to contract performance"
],
"proeth:withinCompetence": false,
"rdfs:label": "Low Bid Submission"
}
Description: At the pre-construction conference, Engineer A acknowledged the incompleteness of the drawings and specifications only after Engineer C raised the issue and declared portions of the project unbuildable, rather than proactively disclosing the deficiencies to any stakeholder at any earlier point.
Temporal Marker: Pre-construction conference, after contract award to Hi-Lo Construction instant
Fluent Transitions:
- Incompleteness Publicly Acknowledged
- Project Delay Risk Active
- Stakeholder Uninformed of Deficiencies
Mental State: reactive
Intended Outcome: Respond to Engineer C's challenge by acknowledging the known deficiencies while deflecting responsibility to time pressure and anticipated federal funding
Foreseen Unintended Effects:
- Disclosure at this stage provides no remedial benefit to the design process
- Acknowledgment exposes Engineer A to professional and legal scrutiny
Obligation Engagement:
- Obligation to avoid deceptive acts
- Obligation of honest disclosure to client and funding agency
- Obligation to provide complete design drawings and specifications
Guided By Principles:
- Transparency with clients and public agencies
- Honest representation to client
- Public fund stewardship
Required Capabilities:
Field classification (triples vs literals)
violatesObligation: Obligation to avoid deceptive acts; Obligation of honest disclosure to client and funding agency; Obligation to provide complete design drawings and specificationsguidedByPrinciple: Transparency with clients and public agencies; Honest representation to client; Public fund stewardshipinitiates: Incompleteness Publicly Acknowledged; Project Delay Risk Activeterminates: Stakeholder Uninformed of Deficiencies
descriptioncontent: At the pre-construction conference, Engineer A acknowledged the incompleteness of the drawings and specifications only after Engineer C raised the issue and declared portions of the project unbuildable, rather than proactively disclosing the deficiencies to any stakeholder at any earlier point.hasAgentcontent: Engineer AtemporalMarkercontent: Pre-construction conference, after contract award to Hi-Lo ConstructioneventRoleContextcontent: Design EngineerhasMentalStatecontent: reactiveintendedOutcomecontent: Respond to Engineer C's challenge by acknowledging the known deficiencies while deflecting responsibility to time pressure and anticipated federal fundingforeseenUnintendedEffectscontent: Disclosure at this stage provides no remedial benefit to the design process; Acknowledgment exposes Engineer A to professional and legal scrutinytemporalExtentcontent: instanttemporalSequencecontent: 14withinCompetenceassessment: True
requiresCapability: Professional candor; Timely disclosure of known deficiencies
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Action_Reactive_Incompleteness_Acknowledgment",
"@type": "proeth:Action",
"proeth:description": "At the pre-construction conference, Engineer A acknowledged the incompleteness of the drawings and specifications only after Engineer C raised the issue and declared portions of the project unbuildable, rather than proactively disclosing the deficiencies to any stakeholder at any earlier point.",
"proeth:eventRoleContext": "Design Engineer",
"proeth:foreseenUnintendedEffects": [
"Disclosure at this stage provides no remedial benefit to the design process",
"Acknowledgment exposes Engineer A to professional and legal scrutiny"
],
"proeth:fulfillsObligation": [],
"proeth:guidedByPrinciple": [
"Transparency with clients and public agencies",
"Honest representation to client",
"Public fund stewardship"
],
"proeth:hasAgent": "Engineer A",
"proeth:hasMentalState": "reactive",
"proeth:initiates": [
"Incompleteness Publicly Acknowledged",
"Project Delay Risk Active"
],
"proeth:intendedOutcome": "Respond to Engineer C\u0027s challenge by acknowledging the known deficiencies while deflecting responsibility to time pressure and anticipated federal funding",
"proeth:raisesObligation": [],
"proeth:requiresCapability": [
"Professional candor",
"Timely disclosure of known deficiencies"
],
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Pre-construction conference, after contract award to Hi-Lo Construction",
"proeth:temporalSequence": 14,
"proeth:terminates": [
"Stakeholder Uninformed of Deficiencies"
],
"proeth:violatesObligation": [
"Obligation to avoid deceptive acts",
"Obligation of honest disclosure to client and funding agency",
"Obligation to provide complete design drawings and specifications"
],
"proeth:withinCompetence": true,
"rdfs:label": "Reactive Incompleteness Acknowledgment"
}
Extracted Events (9)
Occurrences that trigger ethical considerations and state changesDescription: The dam project was partially funded by a federal grant, which brought federal oversight requirements and Engineer B's review role into the project.
Temporal Marker: Pre-design phase, established before RFP issuance interval
Fluent Transitions:
- Federal Oversight Active
- Federal Review Requirement
Causes State Change: Federal funding and associated federal agency oversight became part of the project structure, introducing a second reviewing authority.
Field classification (triples vs literals)
initiates: Federal Oversight Active; Federal Review Requirement
descriptioncontent: The dam project was partially funded by a federal grant, which brought federal oversight requirements and Engineer B's review role into the project.temporalMarkercontent: Pre-design phase, established before RFP issuanceeventTypecontent: exogenouscausesStateChangecontent: Federal funding and associated federal agency oversight became part of the project structure, introducing a second reviewing authority.temporalExtentcontent: intervaltemporalSequencecontent: 1severityassessment: medium
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Federal_Grant_Involvement",
"@type": "proeth:Event",
"proeth:causesStateChange": "Federal funding and associated federal agency oversight became part of the project structure, introducing a second reviewing authority.",
"proeth:description": "The dam project was partially funded by a federal grant, which brought federal oversight requirements and Engineer B\u0027s review role into the project.",
"proeth:eventType": "exogenous",
"proeth:initiates": [
"Federal Oversight Active",
"Federal Review Requirement"
],
"proeth:severity": "medium",
"proeth:temporalExtent": "interval",
"proeth:temporalMarker": "Pre-design phase, established before RFP issuance",
"proeth:temporalSequence": 1,
"rdfs:label": "Federal Grant Involvement"
}
Description: Engineer A's firm was awarded the design contract by the local public agency following submission of an impressive brochure and completion of a personal interview.
Temporal Marker: Early project phase, after RFP response and interview instant
Fluent Transitions:
- Active Design Contract
- Professional Responsibility Incumbent on Engineer A
- Open Competitive Bidding State for Design Services
Causes State Change: Engineer A's firm transitioned from bidder status to contracted design engineer for the dam project.
Caused By Action: Action_RFP_Response_Submission
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_RFP_Response_Submissioninitiates: Active Design Contract; Professional Responsibility Incumbent on Engineer Aterminates: Open Competitive Bidding State for Design Services
descriptioncontent: Engineer A's firm was awarded the design contract by the local public agency following submission of an impressive brochure and completion of a personal interview.temporalMarkercontent: Early project phase, after RFP response and intervieweventTypecontent: outcomecausesStateChangecontent: Engineer A's firm transitioned from bidder status to contracted design engineer for the dam project.temporalExtentcontent: instanttemporalSequencecontent: 3severityassessment: routine
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Design_Contract_Award",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_RFP_Response_Submission",
"proeth:causesStateChange": "Engineer A\u0027s firm transitioned from bidder status to contracted design engineer for the dam project.",
"proeth:description": "Engineer A\u0027s firm was awarded the design contract by the local public agency following submission of an impressive brochure and completion of a personal interview.",
"proeth:eventType": "outcome",
"proeth:initiates": [
"Active Design Contract",
"Professional Responsibility Incumbent on Engineer A"
],
"proeth:severity": "routine",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Early project phase, after RFP response and interview",
"proeth:temporalSequence": 3,
"proeth:terminates": [
"Open Competitive Bidding State for Design Services"
],
"rdfs:label": "Design Contract Award"
}
Description: Engineer A's drawings and specifications were produced in a knowingly incomplete state, creating a condition of deficient project documentation that would affect all downstream project phases.
Temporal Marker: Design phase, prior to document submission for review interval
Fluent Transitions:
- Deficient Documentation State
- Public Safety Risk
- Contractor Exposure to Ambiguity
- Complete Design Deliverable Expected State
Causes State Change: Project documentation entered a deficient state, with gaps that made construction guidance unreliable and portions of the project potentially unbuildable.
Caused By Action: Action_Incomplete_Work_Submission
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Incomplete_Work_Submissioninitiates: Deficient Documentation State; Public Safety Risk; Contractor Exposure to Ambiguityterminates: Complete Design Deliverable Expected State
descriptioncontent: Engineer A's drawings and specifications were produced in a knowingly incomplete state, creating a condition of deficient project documentation that would affect all downstream project phases.temporalMarkercontent: Design phase, prior to document submission for revieweventTypecontent: outcomecausesStateChangecontent: Project documentation entered a deficient state, with gaps that made construction guidance unreliable and portions of the project potentially unbuildable.temporalExtentcontent: intervaltemporalSequencecontent: 4severityassessment: high
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Document_Incompleteness_Occurrence",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Incomplete_Work_Submission",
"proeth:causesStateChange": "Project documentation entered a deficient state, with gaps that made construction guidance unreliable and portions of the project potentially unbuildable.",
"proeth:description": "Engineer A\u0027s drawings and specifications were produced in a knowingly incomplete state, creating a condition of deficient project documentation that would affect all downstream project phases.",
"proeth:eventType": "outcome",
"proeth:initiates": [
"Deficient Documentation State",
"Public Safety Risk",
"Contractor Exposure to Ambiguity"
],
"proeth:severity": "high",
"proeth:temporalExtent": "interval",
"proeth:temporalMarker": "Design phase, prior to document submission for review",
"proeth:temporalSequence": 4,
"proeth:terminates": [
"Complete Design Deliverable Expected State"
],
"rdfs:label": "Document Incompleteness Occurrence"
}
Description: Engineer B, acting as the federal funding agency's engineering staff reviewer, completed a review of the incomplete documents and approved them without identifying or flagging the deficiencies.
Temporal Marker: Post-submission, prior to bid advertisement instant
Fluent Transitions:
- Federally Approved Deficient Documents State
- Bid Advertisement Permissible State
- Federal Review Pending State
Causes State Change: The incomplete documents acquired an official federal approval status, removing a gatekeeping barrier and allowing the deficient project to advance to public bidding.
Caused By Action: Action_Incomplete_Documents_Approval
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Incomplete_Documents_Approvalinitiates: Federally Approved Deficient Documents State; Bid Advertisement Permissible Stateterminates: Federal Review Pending State
descriptioncontent: Engineer B, acting as the federal funding agency's engineering staff reviewer, completed a review of the incomplete documents and approved them without identifying or flagging the deficiencies.temporalMarkercontent: Post-submission, prior to bid advertisementeventTypecontent: outcomecausesStateChangecontent: The incomplete documents acquired an official federal approval status, removing a gatekeeping barrier and allowing the deficient project to advance to public bidding.temporalExtentcontent: instanttemporalSequencecontent: 8severityassessment: high
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Federal_Review_Completion",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Incomplete_Documents_Approval",
"proeth:causesStateChange": "The incomplete documents acquired an official federal approval status, removing a gatekeeping barrier and allowing the deficient project to advance to public bidding.",
"proeth:description": "Engineer B, acting as the federal funding agency\u0027s engineering staff reviewer, completed a review of the incomplete documents and approved them without identifying or flagging the deficiencies.",
"proeth:eventType": "outcome",
"proeth:initiates": [
"Federally Approved Deficient Documents State",
"Bid Advertisement Permissible State"
],
"proeth:severity": "high",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "Post-submission, prior to bid advertisement",
"proeth:temporalSequence": 8,
"proeth:terminates": [
"Federal Review Pending State"
],
"rdfs:label": "Federal Review Completion"
}
Description: The dam project was advertised for bids to the public following federal approval of the incomplete documents, initiating the contractor selection process.
Temporal Marker: After federal approval, prior to bid submission deadline interval
Fluent Transitions:
- Open Bidding State
- Contractor Exposure to Deficient Documents
- Pre-Bid Design Phase
Causes State Change: The project entered the public procurement phase, exposing contractors to the deficient documents as the basis for their bids.
Caused By Action: Action_Incomplete_Documents_Approval
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Incomplete_Documents_Approvalinitiates: Open Bidding State; Contractor Exposure to Deficient Documentsterminates: Pre-Bid Design Phase
descriptioncontent: The dam project was advertised for bids to the public following federal approval of the incomplete documents, initiating the contractor selection process.temporalMarkercontent: After federal approval, prior to bid submission deadlineeventTypecontent: automatic_triggercausesStateChangecontent: The project entered the public procurement phase, exposing contractors to the deficient documents as the basis for their bids.temporalExtentcontent: intervaltemporalSequencecontent: 9severityassessment: medium
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Bid_Advertisement",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Incomplete_Documents_Approval",
"proeth:causesStateChange": "The project entered the public procurement phase, exposing contractors to the deficient documents as the basis for their bids.",
"proeth:description": "The dam project was advertised for bids to the public following federal approval of the incomplete documents, initiating the contractor selection process.",
"proeth:eventType": "automatic_trigger",
"proeth:initiates": [
"Open Bidding State",
"Contractor Exposure to Deficient Documents"
],
"proeth:severity": "medium",
"proeth:temporalExtent": "interval",
"proeth:temporalMarker": "After federal approval, prior to bid submission deadline",
"proeth:temporalSequence": 9,
"proeth:terminates": [
"Pre-Bid Design Phase"
],
"rdfs:label": "Bid Advertisement"
}
Description: Hi-Lo Construction, owned by Engineer C, was identified as the winning low bidder and awarded the construction contract for the dam project.
Temporal Marker: After bid submission deadline, prior to pre-construction conference instant
Fluent Transitions:
- Active Construction Contract
- Contractor Bound to Deficient Documents
- Open Bidding State
Causes State Change: Engineer C's firm transitioned from bidder to awarded contractor, taking on construction responsibility under documents that were deficient.
Caused By Action: Action_Low_Bid_Submission
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Low_Bid_Submissioninitiates: Active Construction Contract; Contractor Bound to Deficient Documentsterminates: Open Bidding State
descriptioncontent: Hi-Lo Construction, owned by Engineer C, was identified as the winning low bidder and awarded the construction contract for the dam project.temporalMarkercontent: After bid submission deadline, prior to pre-construction conferenceeventTypecontent: automatic_triggercausesStateChangecontent: Engineer C's firm transitioned from bidder to awarded contractor, taking on construction responsibility under documents that were deficient.temporalExtentcontent: instanttemporalSequencecontent: 11severityassessment: medium
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Contract_Award_to_Contractor",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Low_Bid_Submission",
"proeth:causesStateChange": "Engineer C\u0027s firm transitioned from bidder to awarded contractor, taking on construction responsibility under documents that were deficient.",
"proeth:description": "Hi-Lo Construction, owned by Engineer C, was identified as the winning low bidder and awarded the construction contract for the dam project.",
"proeth:eventType": "automatic_trigger",
"proeth:initiates": [
"Active Construction Contract",
"Contractor Bound to Deficient Documents"
],
"proeth:severity": "medium",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "After bid submission deadline, prior to pre-construction conference",
"proeth:temporalSequence": 11,
"proeth:terminates": [
"Open Bidding State"
],
"rdfs:label": "Contract Award to Contractor"
}
Description: A pre-construction conference was convened bringing together Engineer A, Engineer C, and the agency, at which the deficiencies in the project documents were first openly discussed.
Temporal Marker: After contract award, before construction commencement instant
Fluent Transitions:
- Disclosed Incompleteness State
- Construction Start Pending State
- Non-Disclosure of Incompleteness State
Causes State Change: All key parties were assembled in a formal setting where document deficiencies became the subject of open acknowledgment, moving the incompleteness from a concealed state to a disclosed state.
Field classification (triples vs literals)
initiates: Disclosed Incompleteness State; Construction Start Pending Stateterminates: Non-Disclosure of Incompleteness State
descriptioncontent: A pre-construction conference was convened bringing together Engineer A, Engineer C, and the agency, at which the deficiencies in the project documents were first openly discussed.temporalMarkercontent: After contract award, before construction commencementeventTypecontent: automatic_triggercausesStateChangecontent: All key parties were assembled in a formal setting where document deficiencies became the subject of open acknowledgment, moving the incompleteness from a concealed state to a disclosed state.temporalExtentcontent: instanttemporalSequencecontent: 12severityassessment: high
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Pre-Construction_Conference",
"@type": "proeth:Event",
"proeth:causesStateChange": "All key parties were assembled in a formal setting where document deficiencies became the subject of open acknowledgment, moving the incompleteness from a concealed state to a disclosed state.",
"proeth:description": "A pre-construction conference was convened bringing together Engineer A, Engineer C, and the agency, at which the deficiencies in the project documents were first openly discussed.",
"proeth:eventType": "automatic_trigger",
"proeth:initiates": [
"Disclosed Incompleteness State",
"Construction Start Pending State"
],
"proeth:severity": "high",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "After contract award, before construction commencement",
"proeth:temporalSequence": 12,
"proeth:terminates": [
"Non-Disclosure of Incompleteness State"
],
"rdfs:label": "Pre-Construction Conference"
}
Description: At the pre-construction conference, Engineer C declared that portions of the dam project were unbuildable, surfacing the practical construction consequences of the document deficiencies.
Temporal Marker: During the pre-construction conference instant
Fluent Transitions:
- Constructability Impasse
- Public Safety Risk
- Project Dispute State
- Construction Start Permissible State
Causes State Change: The project's constructability was formally placed in question, creating an impasse that prevented construction from proceeding as documented and exposing the full scope of the document deficiencies.
Caused By Action: Action_Reactive_Incompleteness_Acknowledgment
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Reactive_Incompleteness_Acknowledgmentinitiates: Constructability Impasse; Public Safety Risk; Project Dispute Stateterminates: Construction Start Permissible State
descriptioncontent: At the pre-construction conference, Engineer C declared that portions of the dam project were unbuildable, surfacing the practical construction consequences of the document deficiencies.temporalMarkercontent: During the pre-construction conferenceeventTypecontent: outcomecausesStateChangecontent: The project's constructability was formally placed in question, creating an impasse that prevented construction from proceeding as documented and exposing the full scope of the document deficiencies.temporalExtentcontent: instanttemporalSequencecontent: 13severityassessment: critical
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Unbuildability_Declaration",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Reactive_Incompleteness_Acknowledgment",
"proeth:causesStateChange": "The project\u0027s constructability was formally placed in question, creating an impasse that prevented construction from proceeding as documented and exposing the full scope of the document deficiencies.",
"proeth:description": "At the pre-construction conference, Engineer C declared that portions of the dam project were unbuildable, surfacing the practical construction consequences of the document deficiencies.",
"proeth:eventType": "outcome",
"proeth:initiates": [
"Constructability Impasse",
"Public Safety Risk",
"Project Dispute State"
],
"proeth:severity": "critical",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "During the pre-construction conference",
"proeth:temporalSequence": 13,
"proeth:terminates": [
"Construction Start Permissible State"
],
"rdfs:label": "Unbuildability Declaration"
}
Description: Engineer A acknowledged at the pre-construction conference that the submitted drawings and specifications were incomplete, confirming what had previously been concealed from the agency and contractor.
Temporal Marker: During the pre-construction conference, following Engineer C's declaration instant
Fluent Transitions:
- Official Incompleteness Record
- Remediation Required State
- Engineer A Liability Exposure
- Non-Disclosure of Incompleteness State
Causes State Change: The incompleteness of the project documents became a matter of official record acknowledged by the design engineer, triggering formal accountability and the need for remediation.
Caused By Action: Action_Reactive_Incompleteness_Acknowledgment
Field classification (triples vs literals)
causedByAction: http://proethica.org/cases/85#Action_Reactive_Incompleteness_Acknowledgmentinitiates: Official Incompleteness Record; Remediation Required State; Engineer A Liability Exposureterminates: Non-Disclosure of Incompleteness State
descriptioncontent: Engineer A acknowledged at the pre-construction conference that the submitted drawings and specifications were incomplete, confirming what had previously been concealed from the agency and contractor.temporalMarkercontent: During the pre-construction conference, following Engineer C's declarationeventTypecontent: outcomecausesStateChangecontent: The incompleteness of the project documents became a matter of official record acknowledged by the design engineer, triggering formal accountability and the need for remediation.temporalExtentcontent: instanttemporalSequencecontent: 15severityassessment: high
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#",
"time": "http://www.w3.org/2006/time#"
},
"@id": "http://proethica.org/cases/85#Event_Incompleteness_Acknowledgment_Event",
"@type": "proeth:Event",
"proeth:causedByAction": "http://proethica.org/cases/85#Action_Reactive_Incompleteness_Acknowledgment",
"proeth:causesStateChange": "The incompleteness of the project documents became a matter of official record acknowledged by the design engineer, triggering formal accountability and the need for remediation.",
"proeth:description": "Engineer A acknowledged at the pre-construction conference that the submitted drawings and specifications were incomplete, confirming what had previously been concealed from the agency and contractor.",
"proeth:eventType": "outcome",
"proeth:initiates": [
"Official Incompleteness Record",
"Remediation Required State",
"Engineer A Liability Exposure"
],
"proeth:severity": "high",
"proeth:temporalExtent": "instant",
"proeth:temporalMarker": "During the pre-construction conference, following Engineer C\u0027s declaration",
"proeth:temporalSequence": 15,
"proeth:terminates": [
"Non-Disclosure of Incompleteness State"
],
"rdfs:label": "Incompleteness Acknowledgment Event"
}
Causal Chains (10)
NESS test analysis: Necessary Element of Sufficient SetCausal Language: At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lacking
Necessary Factors (NESS):
- Award of construction contract to Hi-Lo
- Standard pre-construction conference practice
- Parties available to convene
Sufficient Factors:
- Contract award triggering the standard pre-construction conference
Responsibility Attribution:
Agent: Local public agency / project parties
Type: indirect
Within Agent Control:
Yes
Causal Sequence:
-
Contract Award to Contractor
Hi-Lo awarded the contract -
Pre-Construction Conference
Parties convene to begin project planning
Field classification (triples vs literals)
cause: Contract Award to Contractoreffect: Pre-Construction ConferenceresponsibleAgent: Local public agency / project parties
causalLanguagecontent: At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lackingnecessaryFactorscontent: Award of construction contract to Hi-Lo; Standard pre-construction conference practice; Parties available to convenesufficientFactorscontent: Contract award triggering the standard pre-construction conferencecounterfactualcontent: Without the contract award, the pre-construction conference would not have been convenedcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Contract Award to Contractor', 'proeth:description': 'Hi-Lo awarded the contract'}; {'proeth:step': 2, 'proeth:element': 'Pre-Construction Conference', 'proeth:description': 'Parties convene to begin project planning'}responsibilityTypeassessment: indirectwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_ea4423c2",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lacking",
"proeth:causalSequence": [
{
"proeth:description": "Hi-Lo awarded the contract",
"proeth:element": "Contract Award to Contractor",
"proeth:step": 1
},
{
"proeth:description": "Parties convene to begin project planning",
"proeth:element": "Pre-Construction Conference",
"proeth:step": 2
}
],
"proeth:cause": "Contract Award to Contractor",
"proeth:counterfactual": "Without the contract award, the pre-construction conference would not have been convened",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Pre-Construction Conference",
"proeth:necessaryFactors": [
"Award of construction contract to Hi-Lo",
"Standard pre-construction conference practice",
"Parties available to convene"
],
"proeth:responsibilityType": "indirect",
"proeth:responsibleAgent": "Local public agency / project parties",
"proeth:sufficientFactors": [
"Contract award triggering the standard pre-construction conference"
],
"proeth:withinAgentControl": true
}
Causal Language: Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified date... while much of the information was missing from the drawings and specifications
Necessary Factors (NESS):
- Engineer A's decision to submit despite incompleteness
- Time pressure to deliver by a specified date
- Engineer A's expectation that federal funds would cover added costs
Sufficient Factors:
- Decision to deliver incomplete documents under deadline pressure with reliance on federal funding
Responsibility Attribution:
Agent: Engineer A
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
Incomplete Work Submission
Engineer A submits knowingly incomplete drawings and specifications -
Document Incompleteness Occurrence
Drawings and specifications exist in a knowingly incomplete state
Field classification (triples vs literals)
cause: Incomplete Work Submissioneffect: Document Incompleteness OccurrenceresponsibleAgent: Engineer A
causalLanguagecontent: Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified date... while much of the information was missing from the drawings and specificationsnecessaryFactorscontent: Engineer A's decision to submit despite incompleteness; Time pressure to deliver by a specified date; Engineer A's expectation that federal funds would cover added costssufficientFactorscontent: Decision to deliver incomplete documents under deadline pressure with reliance on federal fundingcounterfactualcontent: Had Engineer A completed the full design as required, the incompleteness would not have occurredcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Incomplete Work Submission', 'proeth:description': 'Engineer A submits knowingly incomplete drawings and specifications'}; {'proeth:step': 2, 'proeth:element': 'Document Incompleteness Occurrence', 'proeth:description': 'Drawings and specifications exist in a knowingly incomplete state'}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_c004351d",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "Engineer A decided to submit drawings and specifications that he knew to be incomplete by the specified date... while much of the information was missing from the drawings and specifications",
"proeth:causalSequence": [
{
"proeth:description": "Engineer A submits knowingly incomplete drawings and specifications",
"proeth:element": "Incomplete Work Submission",
"proeth:step": 1
},
{
"proeth:description": "Drawings and specifications exist in a knowingly incomplete state",
"proeth:element": "Document Incompleteness Occurrence",
"proeth:step": 2
}
],
"proeth:cause": "Incomplete Work Submission",
"proeth:counterfactual": "Had Engineer A completed the full design as required, the incompleteness would not have occurred",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Document Incompleteness Occurrence",
"proeth:necessaryFactors": [
"Engineer A\u0027s decision to submit despite incompleteness",
"Time pressure to deliver by a specified date",
"Engineer A\u0027s expectation that federal funds would cover added costs"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer A",
"proeth:sufficientFactors": [
"Decision to deliver incomplete documents under deadline pressure with reliance on federal funding"
],
"proeth:withinAgentControl": true
}
Causal Language: did not inform anyone as to their incompleteness
Necessary Factors (NESS):
- Engineer A's silence about the incompleteness
- Engineer B's lack of independent identification of the defects
- Local agency's lack of in-house technical review capability
Sufficient Factors:
- Non-disclosure combined with inadequate federal review
Responsibility Attribution:
Agent: Engineer A
Type: shared
Within Agent Control:
Yes
Causal Sequence:
-
Non-Disclosure of Incompleteness
Engineer A withholds knowledge of incompleteness from all parties -
Federal Review Completion
Engineer B reviews the incomplete plans without catching defects -
Incomplete Documents Approval
Engineer B approves the incomplete drawings and specifications
Field classification (triples vs literals)
cause: Non-Disclosure of Incompletenesseffect: Incomplete Documents ApprovalresponsibleAgent: Engineer A
causalLanguagecontent: did not inform anyone as to their incompletenessnecessaryFactorscontent: Engineer A's silence about the incompleteness; Engineer B's lack of independent identification of the defects; Local agency's lack of in-house technical review capabilitysufficientFactorscontent: Non-disclosure combined with inadequate federal reviewcounterfactualcontent: Had Engineer A disclosed the incompleteness, Engineer B would likely not have approved the planscausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Non-Disclosure of Incompleteness', 'proeth:description': 'Engineer A withholds knowledge of incompleteness from all parties'}; {'proeth:step': 2, 'proeth:element': 'Federal Review Completion', 'proeth:description': 'Engineer B reviews the incomplete plans without catching defects'}; {'proeth:step': 3, 'proeth:element': 'Incomplete Documents Approval', 'proeth:description': 'Engineer B approves the incomplete drawings and specifications'}responsibilityTypeassessment: sharedwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_ff7980a3",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "did not inform anyone as to their incompleteness",
"proeth:causalSequence": [
{
"proeth:description": "Engineer A withholds knowledge of incompleteness from all parties",
"proeth:element": "Non-Disclosure of Incompleteness",
"proeth:step": 1
},
{
"proeth:description": "Engineer B reviews the incomplete plans without catching defects",
"proeth:element": "Federal Review Completion",
"proeth:step": 2
},
{
"proeth:description": "Engineer B approves the incomplete drawings and specifications",
"proeth:element": "Incomplete Documents Approval",
"proeth:step": 3
}
],
"proeth:cause": "Non-Disclosure of Incompleteness",
"proeth:counterfactual": "Had Engineer A disclosed the incompleteness, Engineer B would likely not have approved the plans",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Incomplete Documents Approval",
"proeth:necessaryFactors": [
"Engineer A\u0027s silence about the incompleteness",
"Engineer B\u0027s lack of independent identification of the defects",
"Local agency\u0027s lack of in-house technical review capability"
],
"proeth:responsibilityType": "shared",
"proeth:responsibleAgent": "Engineer A",
"proeth:sufficientFactors": [
"Non-disclosure combined with inadequate federal review"
],
"proeth:withinAgentControl": true
}
Causal Language: the project is thereafter duly advertised for bids and a contract is awarded to the low bidder, Hi-Lo Construction
Necessary Factors (NESS):
- Public advertisement of the project for bids
- Engineer C's decision to bid
- Available bidding documents for review
Sufficient Factors:
- Advertised project opportunity prompting Hi-Lo's bid submission
Responsibility Attribution:
Agent: Engineer C
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
Bid Advertisement
Project advertised to the public for bids -
Low Bid Submission
Engineer C submits the low bid for Hi-Lo Construction
Field classification (triples vs literals)
cause: Bid Advertisementeffect: Low Bid SubmissionresponsibleAgent: Engineer C
causalLanguagecontent: the project is thereafter duly advertised for bids and a contract is awarded to the low bidder, Hi-Lo ConstructionnecessaryFactorscontent: Public advertisement of the project for bids; Engineer C's decision to bid; Available bidding documents for reviewsufficientFactorscontent: Advertised project opportunity prompting Hi-Lo's bid submissioncounterfactualcontent: Without the bid advertisement, Engineer C could not have submitted a bidcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Bid Advertisement', 'proeth:description': 'Project advertised to the public for bids'}; {'proeth:step': 2, 'proeth:element': 'Low Bid Submission', 'proeth:description': 'Engineer C submits the low bid for Hi-Lo Construction'}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_d039dddd",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "the project is thereafter duly advertised for bids and a contract is awarded to the low bidder, Hi-Lo Construction",
"proeth:causalSequence": [
{
"proeth:description": "Project advertised to the public for bids",
"proeth:element": "Bid Advertisement",
"proeth:step": 1
},
{
"proeth:description": "Engineer C submits the low bid for Hi-Lo Construction",
"proeth:element": "Low Bid Submission",
"proeth:step": 2
}
],
"proeth:cause": "Bid Advertisement",
"proeth:counterfactual": "Without the bid advertisement, Engineer C could not have submitted a bid",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Low Bid Submission",
"proeth:necessaryFactors": [
"Public advertisement of the project for bids",
"Engineer C\u0027s decision to bid",
"Available bidding documents for review"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer C",
"proeth:sufficientFactors": [
"Advertised project opportunity prompting Hi-Lo\u0027s bid submission"
],
"proeth:withinAgentControl": true
}
Causal Language: a contract is awarded to the low bidder, Hi-Lo Construction
Necessary Factors (NESS):
- Engineer C's submission of the lowest bid
- Standard low-bidder award process
- Completion of bid advertisement
Sufficient Factors:
- Submission of the lowest bid in a low-bid procurement
Responsibility Attribution:
Agent: Engineer C
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
Low Bid Submission
Engineer C submits lowest bid -
Contract Award to Contractor
Hi-Lo Construction awarded the construction contract
Field classification (triples vs literals)
cause: Low Bid Submissioneffect: Contract Award to ContractorresponsibleAgent: Engineer C
causalLanguagecontent: a contract is awarded to the low bidder, Hi-Lo ConstructionnecessaryFactorscontent: Engineer C's submission of the lowest bid; Standard low-bidder award process; Completion of bid advertisementsufficientFactorscontent: Submission of the lowest bid in a low-bid procurementcounterfactualcontent: Without submitting the low bid, Hi-Lo would not have been awarded the contractcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Low Bid Submission', 'proeth:description': 'Engineer C submits lowest bid'}; {'proeth:step': 2, 'proeth:element': 'Contract Award to Contractor', 'proeth:description': 'Hi-Lo Construction awarded the construction contract'}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_f0d7bc08",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "a contract is awarded to the low bidder, Hi-Lo Construction",
"proeth:causalSequence": [
{
"proeth:description": "Engineer C submits lowest bid",
"proeth:element": "Low Bid Submission",
"proeth:step": 1
},
{
"proeth:description": "Hi-Lo Construction awarded the construction contract",
"proeth:element": "Contract Award to Contractor",
"proeth:step": 2
}
],
"proeth:cause": "Low Bid Submission",
"proeth:counterfactual": "Without submitting the low bid, Hi-Lo would not have been awarded the contract",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Contract Award to Contractor",
"proeth:necessaryFactors": [
"Engineer C\u0027s submission of the lowest bid",
"Standard low-bidder award process",
"Completion of bid advertisement"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer C",
"proeth:sufficientFactors": [
"Submission of the lowest bid in a low-bid procurement"
],
"proeth:withinAgentControl": true
}
Causal Language: At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lacking in the drawings and specifications and that Hi-Lo Construction declares that certain parts of the project are "unbuildable" without major changes
Necessary Factors (NESS):
- Convening of the pre-construction conference
- Engineer C's review identifying missing design detail
- Pre-existing document incompleteness
Sufficient Factors:
- Conference forum combined with Engineer C's recognition of incomplete documents
Responsibility Attribution:
Agent: Engineer C
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
Pre-Construction Conference
Parties convene for the conference -
Unbuildability Declaration
Engineer C declares parts of the project unbuildable without major changes
Field classification (triples vs literals)
cause: Pre-Construction Conferenceeffect: Unbuildability DeclarationresponsibleAgent: Engineer C
causalLanguagecontent: At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lacking in the drawings and specifications and that Hi-Lo Construction declares that certain parts of the project are "unbuildable" without major changesnecessaryFactorscontent: Convening of the pre-construction conference; Engineer C's review identifying missing design detail; Pre-existing document incompletenesssufficientFactorscontent: Conference forum combined with Engineer C's recognition of incomplete documentscounterfactualcontent: Without the conference, Engineer C's unbuildability declaration would not have been made at that pointcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Pre-Construction Conference', 'proeth:description': 'Parties convene for the conference'}; {'proeth:step': 2, 'proeth:element': 'Unbuildability Declaration', 'proeth:description': 'Engineer C declares parts of the project unbuildable without major changes'}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_2d61c4e0",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "At the pre-construction conference, it is pointed out by Engineer C, owner of Hi-Lo Construction, that much of the design detail is lacking in the drawings and specifications and that Hi-Lo Construction declares that certain parts of the project are \"unbuildable\" without major changes",
"proeth:causalSequence": [
{
"proeth:description": "Parties convene for the conference",
"proeth:element": "Pre-Construction Conference",
"proeth:step": 1
},
{
"proeth:description": "Engineer C declares parts of the project unbuildable without major changes",
"proeth:element": "Unbuildability Declaration",
"proeth:step": 2
}
],
"proeth:cause": "Pre-Construction Conference",
"proeth:counterfactual": "Without the conference, Engineer C\u0027s unbuildability declaration would not have been made at that point",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Unbuildability Declaration",
"proeth:necessaryFactors": [
"Convening of the pre-construction conference",
"Engineer C\u0027s review identifying missing design detail",
"Pre-existing document incompleteness"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer C",
"proeth:sufficientFactors": [
"Conference forum combined with Engineer C\u0027s recognition of incomplete documents"
],
"proeth:withinAgentControl": true
}
Causal Language: Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date
Necessary Factors (NESS):
- Engineer C's declaration of unbuildability
- Engineer A's presence at the conference
- Engineer A's awareness that documents were incomplete
Sufficient Factors:
- Engineer C's challenge prompting Engineer A's defensive acknowledgment
Responsibility Attribution:
Agent: Engineer A
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
Unbuildability Declaration
Engineer C declares portions unbuildable -
Reactive Incompleteness Acknowledgment
Engineer A agrees and cites deadline pressure and reliance on federal funds
Field classification (triples vs literals)
cause: Unbuildability Declarationeffect: Reactive Incompleteness AcknowledgmentresponsibleAgent: Engineer A
causalLanguagecontent: Engineer A generally agrees with Hi-Lo's characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified datenecessaryFactorscontent: Engineer C's declaration of unbuildability; Engineer A's presence at the conference; Engineer A's awareness that documents were incompletesufficientFactorscontent: Engineer C's challenge prompting Engineer A's defensive acknowledgmentcounterfactualcontent: Without Engineer C raising the issue, Engineer A would likely not have acknowledged the incompleteness at that timecausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Unbuildability Declaration', 'proeth:description': 'Engineer C declares portions unbuildable'}; {'proeth:step': 2, 'proeth:element': 'Reactive Incompleteness Acknowledgment', 'proeth:description': 'Engineer A agrees and cites deadline pressure and reliance on federal funds'}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_73959084",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "Engineer A generally agrees with Hi-Lo\u0027s characterization, but in his defense responds that he felt pressured to deliver the drawings and specifications on a specified date",
"proeth:causalSequence": [
{
"proeth:description": "Engineer C declares portions unbuildable",
"proeth:element": "Unbuildability Declaration",
"proeth:step": 1
},
{
"proeth:description": "Engineer A agrees and cites deadline pressure and reliance on federal funds",
"proeth:element": "Reactive Incompleteness Acknowledgment",
"proeth:step": 2
}
],
"proeth:cause": "Unbuildability Declaration",
"proeth:counterfactual": "Without Engineer C raising the issue, Engineer A would likely not have acknowledged the incompleteness at that time",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Reactive Incompleteness Acknowledgment",
"proeth:necessaryFactors": [
"Engineer C\u0027s declaration of unbuildability",
"Engineer A\u0027s presence at the conference",
"Engineer A\u0027s awareness that documents were incomplete"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer A",
"proeth:sufficientFactors": [
"Engineer C\u0027s challenge prompting Engineer A\u0027s defensive acknowledgment"
],
"proeth:withinAgentControl": true
}
Causal Language: The signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the project
Necessary Factors (NESS):
- Federal grant partially funding the project
- Federal oversight requirement triggering review
- Engineer B assigned as reviewer
Sufficient Factors:
- Federal funding requiring federal engineering review of the documents
Responsibility Attribution:
Agent: Federal funding agency
Type: indirect
Within Agent Control:
Yes
Causal Sequence:
-
Federal Grant Involvement
Federal grant partially funds the dam project -
Federal Review Completion
Engineer B reviews documents on behalf of federal agency
Field classification (triples vs literals)
cause: Federal Grant Involvementeffect: Federal Review CompletionresponsibleAgent: Federal funding agency
causalLanguagecontent: The signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the projectnecessaryFactorscontent: Federal grant partially funding the project; Federal oversight requirement triggering review; Engineer B assigned as reviewersufficientFactorscontent: Federal funding requiring federal engineering review of the documentscounterfactualcontent: Without the federal grant, the federal agency review by Engineer B would not have been requiredcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Federal Grant Involvement', 'proeth:description': 'Federal grant partially funds the dam project'}; {'proeth:step': 2, 'proeth:element': 'Federal Review Completion', 'proeth:description': 'Engineer B reviews documents on behalf of federal agency'}responsibilityTypeassessment: indirectwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_ce4f3b16",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "The signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the project",
"proeth:causalSequence": [
{
"proeth:description": "Federal grant partially funds the dam project",
"proeth:element": "Federal Grant Involvement",
"proeth:step": 1
},
{
"proeth:description": "Engineer B reviews documents on behalf of federal agency",
"proeth:element": "Federal Review Completion",
"proeth:step": 2
}
],
"proeth:cause": "Federal Grant Involvement",
"proeth:counterfactual": "Without the federal grant, the federal agency review by Engineer B would not have been required",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Federal Review Completion",
"proeth:necessaryFactors": [
"Federal grant partially funding the project",
"Federal oversight requirement triggering review",
"Engineer B assigned as reviewer"
],
"proeth:responsibilityType": "indirect",
"proeth:responsibleAgent": "Federal funding agency",
"proeth:sufficientFactors": [
"Federal funding requiring federal engineering review of the documents"
],
"proeth:withinAgentControl": true
}
Causal Language: Engineer A's firm's impressive brochure and personal interview results in the award of a contract for the design, drawings, and specifications.
Necessary Factors (NESS):
- Engineer A's firm responding to the RFP
- Impressive brochure and personal interview
- Local agency's selection process
Sufficient Factors:
- Combination of submitted RFP response + impressive brochure + successful personal interview
Responsibility Attribution:
Agent: Engineer A's firm
Type: direct
Within Agent Control:
Yes
Causal Sequence:
-
RFP Response Submission
Engineer A's firm responds to the local public agency's RFP with brochure and interview -
Design Contract Award
Local agency awards design contract to Engineer A's firm
Field classification (triples vs literals)
cause: RFP Response Submissioneffect: Design Contract AwardresponsibleAgent: Engineer A's firm
causalLanguagecontent: Engineer A's firm's impressive brochure and personal interview results in the award of a contract for the design, drawings, and specifications.necessaryFactorscontent: Engineer A's firm responding to the RFP; Impressive brochure and personal interview; Local agency's selection processsufficientFactorscontent: Combination of submitted RFP response + impressive brochure + successful personal interviewcounterfactualcontent: Without the RFP response and impressive presentation, Engineer A's firm would not have been awarded the design contractcausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'RFP Response Submission', 'proeth:description': "Engineer A's firm responds to the local public agency's RFP with brochure and interview"}; {'proeth:step': 2, 'proeth:element': 'Design Contract Award', 'proeth:description': "Local agency awards design contract to Engineer A's firm"}responsibilityTypeassessment: directwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_3de9388d",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "Engineer A\u0027s firm\u0027s impressive brochure and personal interview results in the award of a contract for the design, drawings, and specifications.",
"proeth:causalSequence": [
{
"proeth:description": "Engineer A\u0027s firm responds to the local public agency\u0027s RFP with brochure and interview",
"proeth:element": "RFP Response Submission",
"proeth:step": 1
},
{
"proeth:description": "Local agency awards design contract to Engineer A\u0027s firm",
"proeth:element": "Design Contract Award",
"proeth:step": 2
}
],
"proeth:cause": "RFP Response Submission",
"proeth:counterfactual": "Without the RFP response and impressive presentation, Engineer A\u0027s firm would not have been awarded the design contract",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Design Contract Award",
"proeth:necessaryFactors": [
"Engineer A\u0027s firm responding to the RFP",
"Impressive brochure and personal interview",
"Local agency\u0027s selection process"
],
"proeth:responsibilityType": "direct",
"proeth:responsibleAgent": "Engineer A\u0027s firm",
"proeth:sufficientFactors": [
"Combination of submitted RFP response + impressive brochure + successful personal interview"
],
"proeth:withinAgentControl": true
}
Causal Language: the signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the project, and the project is thereafter duly advertised for bids
Necessary Factors (NESS):
- Engineer B's approval of the plans
- Federal funding oversight process
- Existence of project documents to advertise
Sufficient Factors:
- Federal approval triggering the bid advertisement process
Responsibility Attribution:
Agent: Engineer B
Type: indirect
Within Agent Control:
Yes
Causal Sequence:
-
Incomplete Documents Approval
Engineer B approves the incomplete plans -
Bid Advertisement
Project advertised for public bids based on approved documents
Field classification (triples vs literals)
cause: Incomplete Documents Approvaleffect: Bid AdvertisementresponsibleAgent: Engineer B
causalLanguagecontent: the signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the project, and the project is thereafter duly advertised for bidsnecessaryFactorscontent: Engineer B's approval of the plans; Federal funding oversight process; Existence of project documents to advertisesufficientFactorscontent: Federal approval triggering the bid advertisement processcounterfactualcontent: Without Engineer B's approval, the project would not have been advertised for bidscausalSequencecontent: {'proeth:step': 1, 'proeth:element': 'Incomplete Documents Approval', 'proeth:description': 'Engineer B approves the incomplete plans'}; {'proeth:step': 2, 'proeth:element': 'Bid Advertisement', 'proeth:description': 'Project advertised for public bids based on approved documents'}responsibilityTypeassessment: indirectwithinAgentControlassessment: True
RDF JSON-LD
{
"@context": {
"proeth": "http://proethica.org/ontology/intermediate#",
"proeth-case": "http://proethica.org/cases/85#",
"rdf": "http://www.w3.org/1999/02/22-rdf-syntax-ns#",
"rdfs": "http://www.w3.org/2000/01/rdf-schema#"
},
"@id": "http://proethica.org/cases/85#CausalChain_048baa69",
"@type": "proeth:CausalChain",
"proeth:causalLanguage": "the signed and sealed drawings and specifications are ultimately approved by Engineer B of the engineering staff of the federal agency funding the project, and the project is thereafter duly advertised for bids",
"proeth:causalSequence": [
{
"proeth:description": "Engineer B approves the incomplete plans",
"proeth:element": "Incomplete Documents Approval",
"proeth:step": 1
},
{
"proeth:description": "Project advertised for public bids based on approved documents",
"proeth:element": "Bid Advertisement",
"proeth:step": 2
}
],
"proeth:cause": "Incomplete Documents Approval",
"proeth:counterfactual": "Without Engineer B\u0027s approval, the project would not have been advertised for bids",
"proeth:discoveredInSection": "facts",
"proeth:effect": "Bid Advertisement",
"proeth:necessaryFactors": [
"Engineer B\u0027s approval of the plans",
"Federal funding oversight process",
"Existence of project documents to advertise"
],
"proeth:responsibilityType": "indirect",
"proeth:responsibleAgent": "Engineer B",
"proeth:sufficientFactors": [
"Federal approval triggering the bid advertisement process"
],
"proeth:withinAgentControl": true
}
Allen Temporal Relations (12)
Interval algebra relationships with OWL-Time standard properties| From Entity | Allen Relation | To Entity | OWL-Time Property | Evidence |
|---|---|---|---|---|
| RFP issuance by local public agency |
before
Entity1 is before Entity2 |
Engineer A's firm submitting brochure and completing interview |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A responds to an RFP from a small local public agency... Engineer A's firm's impressive bro... [more] |
| Engineer A's firm submitting brochure and completing interview |
before
Entity1 is before Entity2 |
award of design contract to Engineer A |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A's firm's impressive brochure and personal interview results in the award of a contract fo... [more] |
| award of design contract to Engineer A |
before
Entity1 is before Entity2 |
production of drawings and specifications by Engineer A |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A responds to an RFP... results in the award of a contract for the design, drawings, and sp... [more] |
| production of drawings and specifications by Engineer A |
before
Entity1 is before Entity2 |
Engineer B's approval of drawings and specifications |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
The signed and sealed drawings and specifications are ultimately approved by Engineer B of the engin... [more] |
| Engineer B's approval of drawings and specifications |
before
Entity1 is before Entity2 |
project advertised for bids |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
The signed and sealed drawings and specifications are ultimately approved by Engineer B... and the p... [more] |
| project advertised for bids |
before
Entity1 is before Entity2 |
contract awarded to Hi-Lo Construction |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
The project is thereafter duly advertised for bids and a contract is awarded to the low bidder, Hi-L... [more] |
| contract awarded to Hi-Lo Construction |
before
Entity1 is before Entity2 |
pre-construction conference |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
A contract is awarded to the low bidder, Hi-Lo Construction. At the pre-construction conference, it ... [more] |
| Engineer C's review of bidding documents |
before
Entity1 is before Entity2 |
Engineer C submitting low bid |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Presumably, Engineer C had an opportunity to review the bidding documents which included appropriate... [more] |
| Engineer C submitting low bid |
before
Entity1 is before Entity2 |
pre-construction conference |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
A contract is awarded to the low bidder, Hi-Lo Construction. At the pre-construction conference, it ... [more] |
| delivery of drawings and specifications on specified date |
before
Entity1 is before Entity2 |
Engineer A acknowledging incompleteness at pre-construction conference |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A felt pressured to deliver the drawings and specifications on a specified date, but did no... [more] |
| design contract award |
before
Entity1 is before Entity2 |
Engineer A's awareness of time pressure |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A felt pressured to deliver the drawings and specifications on a specified date, but did no... [more] |
| partial federal grant funding commitment |
before
Entity1 is before Entity2 |
RFP issuance |
time:intervalBefore
http://www.w3.org/2006/time#intervalBefore |
Engineer A responds to an RFP from a small local public agency to build a new dam to be financed in ... [more] |
About Allen Relations & OWL-Time
Allen's Interval Algebra provides 13 basic temporal relations between intervals. These relations are mapped to OWL-Time standard properties for interoperability with Semantic Web temporal reasoning systems and SPARQL queries.
Each relation includes both a ProEthica custom property and a
time:* OWL-Time property for maximum compatibility.