Step 1: Contextual Framework Pass (Facts)
Extract roles, states, and resources from the facts section
Engineer's Recommendation For Full-Time, On-Site Project Representative
Step 1 of 5
Facts Section
Section Content:
Facts: The client plans a project and hires Engineer A to furnish complete engineering services for the project. Because of the potentially dangerous nature of implementing the design during the construction phase, Engineer A recommends to the client that a full-time, on-site project representative be hired for the project. After reviewing the completed project plans and costs, the client indicates to Engineer A that the project would be too costly if such a representative were hired. Engineer A proceeds with his work on the project.