Engineer’s Obligation to Consider Feasible Options

Case 123 Source
Back to Case

Document Structure

4

Sections

4/4

With Embeddings

100%

Coverage

384D

Dimensions
Embeddings use 384D local model for precedent matching
Document Sections

Content Length
313 chars
HTML Length
313 chars
Plain Text Length
313 chars
Embedding Dimension
384 Compatible
Created
2026-02-13 16:13
Updated
2026-02-13 16:13
Content Preview
Engineer A has an obligation to advise the state on all feasible and reasonable solutions in an attempt to reach an amicable resolution of this matter, consistent with the interests of the public, including physically moving the historic farmhouse to another appropriate site owned by the family or another party.

Content Length
4937 chars
HTML Length
5146 chars
Plain Text Length
4936 chars
Embedding Dimension
384 Compatible
Created
2026-02-13 16:13
Updated
2026-03-02 23:20
Content Preview
It is not uncommon for professional engineers to be thrust into situations that involve the potential for public controversy and concern, either on an individual basis or more broadly, affecting the larger community. When confronted with such situations, professional engineers have an obligation to be honest and objective in their professional statements and activities. One longstanding example is BER Case 79-2. In that case, Engineer A, the town engineer, and Engineer B, a consulting engineer retained by the town council, collaborated on an assignment to make studies and determine final contours for an existing sanitary landfill, taking into account final land use, environmental concerns, surrounding land use, and topography. Engineers A and B jointly determined that the existing landfill space would be exhausted at the present rate of use in three years, or soon thereafter. The town council had sought an alternate disposal location, but had not been able to locate one. It then requested Engineers A and B to submit new designs for the existing site at higher final contours, in accordance with state environmental laws. After several redesigns were not accepted, the town council requested Engineers A and B to prepare a new design, which resulted in an accepted solution, incorporating minimum setbacks and maximum allowable slopes. This design would provide for a hill more than 100 feet higher than originally proposed. Engineer C, a resident of the town, publicly contended that the higher level design concept would be environmentally unsound because methane gas from the landfill would move into adjacent private property and pollute the nearby ground water. The issue stirred up considerable local publicity and controversy. Engineer C publicly questioned whether Engineers A and B should have agreed to the higher intensity use of the site. In deciding that all professional engineers involved acted ethically, the Board noted that “there is no finite answer to the balance ...

Content Length
854 chars
HTML Length
854 chars
Plain Text Length
854 chars
Embedding Dimension
384 Compatible
Created
2026-02-13 16:13
Updated
2026-02-13 16:13
Content Preview
Engineer A is a professional engineer with JKL Engineering. JKL Engineering has a contract with the state to specify the route for a road connecting two towns. Engineer A determines that the shortest workable route would save approximately 30 minutes from what would otherwise be a two-hour trip. However, in order to build the shortest route, the state would be required to address the impact to a historic family farmhouse that has existed for over 100 years on the land required for the route. Engineer A visits the farmhouse’s owner, who indicates that the family has no interest in selling the farmhouse to the state or to anyone else. Engineer A is aware that the option exists for the state to exercise eminent domain and condemn the farmhouse and allow the state to proceed with the design and construction of the new route between the two towns.

Content Length
66 chars
HTML Length
66 chars
Plain Text Length
66 chars
Embedding Dimension
384 Compatible
Created
2026-02-13 16:13
Updated
2026-02-13 16:13
Content Preview
What are Engineer A’s ethical obligations under the circumstances?
Similar Cases

Find cases with similar D-tuple components, provisions, and tags.

Find Similar Cases

D-tuple Component Breakdown

39

Total Entities

9/9

Components Populated

9/9

With Embeddings

Combined Embedding
Roles R
w=0.12 384D
Engineer A Design Engineer
Determined that the shortest workable route for the state road would save approximately 30 minutes but would require...
JKL Engineering Provider Firm
Holds the contract with the state to specify the route for a road connecting two towns, with Engineer A as the...
State Road Project Client
Commissioned JKL Engineering under contract to specify the route for a road connecting two towns, would be required...
Farmhouse Owner
Owns the historic family farmhouse on the land required for the shortest route, was visited by Engineer A, and...
Board of Ethical Review Adjudicator
Adjudicates the present case, holding that Engineer A has an ethical obligation to balance the interests of all...
Engineer A Public Responsibility
Held by the Board to bear an ethical obligation to balance the interests of all interested and relevant parties,...
Two Towns Affected Municipalities
Named by the Board as interested and relevant parties whose interests Engineer A has an ethical obligation to...
7 entities
Principles P
w=0.2 384D
Greatest Good in Route Selection
The Board holds that Engineer A must balance the interests of the state, the two towns, and the owners of the...
Public Welfare in Route Advice
The Board requires that Engineer A's advice to the state on feasible and reasonable route solutions be consistent...
Honesty in Controversial Statements
The Board frames the case with the value that professional engineers confronted with situations involving potential...
Objectivity in Controversial Statements
The Board frames the case with the value that professional engineers confronted with situations involving potential...
Public Welfare in Route Selection
Engineer A determines the time savings of the shortest workable route for the traveling public, identifies that the...
5 entities
Obligations O
w=0.15 384D
Engineer A Interest Balancing Duty
Engineer A must balance the interests of all interested and relevant parties, including the state, the two towns in...
Engineer A Solutions Advisory Duty
Engineer A must advise the state on feasible and reasonable route solutions, which may include alternative creative...
Engineer A Public Welfare Duty
Engineer A must hold paramount the safety, health, and welfare of the public, including the welfare of the traveling...
JKL Route Specification Duty
JKL Engineering, with Engineer A as the performing professional engineer, must act as a faithful agent of the state...
Engineer A Honest Objective Statements Duty
Engineer A, confronted with a situation involving potential public controversy over the road route and the historic...
5 entities
States S
w=0.1 384D
JKL Road Route Contract
Historic Farmhouse Impact Exposure
Farmhouse Owner Sale Refusal
Eminent Domain Option Availability
Engineer A Material Fact Knowledge
Competing Route Stakeholder Interests
Creative Alternative Solutions Possibility
7 entities
Resources Rs
w=0.1 384D
BER Case 79-2
BER Case 79-2 (topic: professional judgment balancing societal needs against environmental degradation in a landfill...
BER Case 05-4
BER Case 05-4 (topic: whether an engineer must volunteer information at a public hearing that is not, in his...
2 entities
Actions A
w=0.1 384D
Sale Refusal
Route Determination
Property Owner Consultation
Alternative Solutions Recommendation
4 entities
Events E
w=0.08 384D
Farmhouse Impact Discovery
Contract Award
2 entities
Capabilities Ca
w=0.07 384D
Engineer A Route Analysis
Engineer A analyzed the route options for the road connecting two towns, determined that the shortest workable route...
Engineer A Eminent Domain Awareness
Engineer A is aware that eminent domain is a legal option available to the state to condemn the farmhouse and...
Engineer A Objectivity Maintenance
Engineer A, confronted with a situation involving potential public controversy over the road route and the historic...
Engineer A Interest Balancing Reasoning
The Board holds that Engineer A must balance the interests of the state, the two towns, and the owners of the...
Engineer A Solutions Advisory
Engineer A's duty to advise the state on feasible and reasonable route solutions, which may include alternative...
Engineer A Owner Consultation
Engineer A visited the farmhouse owner and learned firsthand that the family has no interest in selling the...
6 entities
Constraints Cs
w=0.08 384D
State Farmhouse Acquisition Boundary
The state must not proceed with the design and construction of the shortest route over the land occupied by the...