Obligation-Conflict Resolution
Case 16-10 (2016) · Public Health, Safety and Welfare-Former Employee's Participation in a Public Safety Standards Hearing
How this case resolved it
No obligation was overridden in this case: the board resolved the
apparent tension without defeat, as recorded below.
Resolved without defeat
The board resolved the apparent tension here by setting a duty's boundary
(specification) or by finding no genuine conflict on the facts
(dissolution), rather than by allowing one obligation to prevail over another.
dissolution
Analytical conclusion 1: The Board did not rank Confidentiality Toward Company X a...
Because Engineer A's general safety knowledge could be separated from Company X's specific confidential business information, the board concluded that both public welfare and confidentiality could be honored simultaneously through scope-limited testimony rather than by subordinating one duty to the other.
specification
Analytical conclusion 4: Q104: Engineer A must distinguish between (a) proprietary...
Given that some of Engineer A's knowledge predates or is independent of the Company X engagement while other knowledge derives from proprietary internal data, the board concluded that Engineer A can testify by relying on the former category and withholding the latter.
What the board concluded
From the Board's conclusions in Case 16-10:
- The NSPE Board of Ethical Review does not believe there is any clear ethical prohibition on Engineer A from participating in the public safety standards hearing as long as (1) Engineer A possesses the technical competence to serve as an engineering expert in the area in which Engineer A is testifying; (2) Engineer A testifies in an objective and truthful manner; and (3) Engineer A does not...