Step 4: Full View

Entities, provisions, decisions, and narrative

Failure To Include Information In Engineering Report
Step 4 of 5

341

Entities

6

Provisions

0

Precedents

20

Questions

28

Conclusions

Transfer

Transformation
Transfer Resolution transfers obligation/responsibility to another party
Full Entity Graph
Loading...
Context: 0 Normative: 0 Temporal: 0 Synthesis: 0
Filter:
Building graph...
Entity Types
Synthesis Reasoning Flow
Shows how NSPE provisions inform questions and conclusions - the board's reasoning chain

The board's deliberative chain: which code provisions informed which ethical questions, and how those questions were resolved. Toggle "Show Entities" to see which entities each provision applies to.

Nodes:
Provision (e.g., I.1.) Question: Board = board-explicit, Impl = implicit, Tens = principle tension, Theo = theoretical, CF = counterfactual Conclusion: Board = board-explicit, Resp = question response, Ext = analytical extension, Synth = principle synthesis Entity (hidden by default)
Edges:
informs answered by applies to
NSPE Code Provisions Referenced
Section II. Rules of Practice 3 126 entities

Engineers shall be objective and truthful in professional reports, statements, or testimony. They shall include all relevant and pertinent information in such reports, statements, or testimony, which should bear the date indicating when it was current.

Applies To (69)
Role
Engineer B Municipality-Retained Litigation Testing Engineer Engineer B produced a report omitting material facts about equipment failure and piles driven to refusal, violating the duty to include all relevant information in professional reports.
Role
Engineer B Adversarial Litigation Testing Supervisor Engineer B's report omitted material facts about the test pile driving program, directly violating the requirement to be objective and truthful and include all pertinent information.
Principle
Completeness and Non-Selectivity Obligation Invoked via Code Requirement This provision directly requires inclusion of all relevant and pertinent information, which is the exact obligation invoked against Engineer B.
Principle
Objectivity Principle Violated by Engineer B Selective Data Use This provision requires objectivity and truthfulness in reports, which Engineer B violated by selectively presenting data.
Principle
Adversarial Objectivity Violated By Engineer B Omitting Wave Equation Results This provision requires complete and objective reporting, directly violated by Engineer B omitting wave equation results.
Principle
Objectivity Principle Violated By Engineer B Selective Reporting This provision mandates truthful and complete reporting, which Engineer B violated by reporting only skin friction calculations.
Principle
Completeness Violated By Engineer B Omitting Equipment Failure This provision requires all relevant information be included, and equipment failure was a material omission from Engineer B's report.
Principle
Omission Materiality Threshold Crossed By Engineer B Wave Equation Omission This provision requires pertinent information be included, and the wave equation results were material findings that were omitted.
Principle
Incomplete Situational Knowledge Restraint Violated By Engineer B Adverse Conclusions Without Full Record Review This provision requires reports to include all relevant information, which Engineer B violated by drawing conclusions without reviewing pile driving records.
Principle
Technical Facts Non-Adversarial Character Invoked in Pile Driving Report Case This provision establishes that reports must be objective and complete regardless of context, supporting the finding that technical facts are non-adversarial.
Principle
Adversarial Engagement Objectivity Obligation Invoked Against Engineer B This provision requires objectivity in reports regardless of who retained the engineer, directly applicable to Engineer B's adversarial context reporting.
Principle
Scope-of-Work Limitation as Incomplete Ethical Defense Invoked for Engineer B Report This provision's requirement to include all relevant information supersedes any contractual scope-of-work limitation as an ethical defense.
Obligation
Engineer B Objective Complete Report Equipment Failure Omission II.3.a. requires engineers to include all relevant and pertinent information in reports, directly obligating Engineer B to disclose the equipment failure.
Obligation
Engineer B Objective Complete Report Wave Equation Omission II.3.a. requires objective and truthful reports with all pertinent information, directly covering the omission of wave equation analysis results.
Obligation
Engineer B Adversarial Context Report Completeness Litigation II.3.a. mandates complete and truthful reporting regardless of context, applying to Engineer B's obligation to produce a non-selective report in litigation.
Obligation
Engineer B Faithful Agent Municipality Report Completeness II.3.a. requires all relevant information be included in reports, directly supporting the obligation to provide a complete and accurate report to the municipality.
Obligation
Engineer B Objective and Complete Reporting Wave Equation Omission II.3.a. explicitly requires inclusion of all relevant and pertinent information, directly matching this obligation regarding wave equation and equipment failure omissions.
Obligation
Engineer B Adversarial Context Report Completeness Non-Selectivity Violation II.3.a. requires complete and truthful reporting, directly applying to the obligation to produce a non-selective report including all material technical findings.
Obligation
Engineer B Adversarial Circumstance Non-Justification Selective Data Use II.3.a. sets a universal standard of completeness and objectivity in reports, directly applying regardless of adversarial circumstances.
Obligation
Engineer B Client Disservice Through Selective Reporting Municipality II.3.a. requires all pertinent information be included, directly prohibiting selective omission of material technical findings that disserve the client.
Obligation
Engineer B Peer Technical Review Opportunity Foreclosure Report Language II.3.a. requires complete and truthful reports, which supports the obligation to ensure report language does not foreclose independent expert review.
Obligation
Engineer B Faithful Agent Obligation Violated by Selective Reporting II.3.a. requires objective and complete reporting, directly applying to the obligation to produce a report that genuinely serves the municipality.
State
Engineer B Report Selective Omission of Pile Driving Records and Equipment Failure Engineer B's report omitted relevant pile driving records and equipment failure data, violating the duty to include all pertinent information.
State
Engineer B Selective Information Omission in Pile Driving Report The pile driving test report submitted to the municipality omitted material information, directly violating the requirement for complete and truthful reporting.
State
Test Pile Program Compromised Conditions Failure to report the compromised test conditions including equipment failure violated the obligation to include all relevant information in the report.
State
Engineer B Failure to Consult Available On-Site Representatives Not consulting available on-site representatives undermined the completeness and objectivity required in professional reports.
State
Engineer B Available Witness Non-Consultation. Contractor and Workers Failing to consult contractor and workers present at the site resulted in an incomplete report lacking all pertinent information.
State
Mediation Proceeding Transparency Obligations Engineers are required to be objective and truthful in testimony, which applies directly to their obligations during mediation proceedings.
Resource
Professional-Report-Integrity-Standard-Pile-Case This provision directly governs the obligation to include all material findings in reports, which is the core standard this resource entity represents.
Resource
NSPE-Code-of-Ethics-Engineer-B-Report This provision is the primary normative authority requiring Engineer B to produce a complete and accurate report including all relevant information.
Resource
Engineer-B-Concluding-Report-Pile-Case This provision applies directly to the expert report found to be materially incomplete by omitting wave equation results and equipment failure information.
Resource
NSPE Code of Ethics - Complete Reporting Obligation This provision is explicitly cited as the governing ethical authority requiring engineers to include all relevant and pertinent information in reports.
Resource
Professional Report Integrity Standard - Pile Driving Test Report This provision is applied to evaluate Engineer B's failure to include material facts in the pile driving test report.
Resource
Pile-Driving-Records-Dock-Project This provision requires that all relevant technical documentation such as pile driving records be objectively and truthfully included or referenced in reports.
Resource
Wave-Equation-Pile-Analysis-Methodology-Instance This provision requires inclusion of all relevant technical methodology results, including wave equation analysis that would have shown piles met design strength.
Action
Selective Omission in Report This provision directly prohibits omitting relevant and pertinent information from engineering reports, which is exactly what selective omission constitutes.
Action
Contradictory Post-Report Explanations This provision requires truthfulness in professional statements, which contradictory post-report explanations violate by being inconsistent with the original report.
Action
Inconsistent Pile Depth Decision Failing to fully and objectively report inconsistent pile depth decisions in the engineering report violates the requirement to include all relevant information.
Action
Vibratory Hammer Substitution Decision The requirement to include all relevant information means the hammer substitution decision should have been fully documented in the report.
Action
Pre-Count Hammer Drop Decision This decision constitutes relevant and pertinent information that must be included in professional engineering reports under this provision.
Event
Geotechnical Report Strength-Gain Anticipation The report must include all relevant and pertinent information including anticipated strength-gain data to be objective and truthful.
Event
30-Day Strength Gain Confirmed Confirmed strength-gain results are pertinent information that should have been included in the engineering report.
Event
Dynamic Test Equipment Failure The failure of dynamic test equipment is relevant information that should be disclosed in professional reports or testimony.
Capability
Engineer B Dynamic Pile Test Equipment Failure Disclosure Failure II.3.a. requires inclusion of all relevant information in reports, directly violated by omitting equipment failure from the concluding report.
Capability
Engineer B Precedent-Based Report Completeness Standard Application Failure II.3.a. mandates objective and complete professional reports, which is the standard Engineer B failed to apply.
Capability
Engineer B Wave Equation Analysis Omission II.3.a. requires all pertinent information be included, and omitting wave equation analysis results violated this requirement.
Capability
Engineer B Dynamic Equipment Failure Non-Disclosure II.3.a. directly requires inclusion of all relevant information, which Engineer B violated by not disclosing equipment failure.
Capability
Engineer B Adversarial Report Completeness and Non-Selectivity II.3.a. requires truthful and complete reports, directly violated by selective omission of material findings.
Capability
Engineer B Faithful Agent Municipality Report Completeness II.3.a. requires complete and truthful reports, which Engineer B failed to provide to the municipality client.
Capability
Engineer B Precedent-Based Report Completeness Standard II.3.a. is the foundational provision requiring complete and pertinent information in reports, which the BER precedent standard reflects.
Capability
Engineer B Selective Information Omission Recognition Failure II.3.a. requires all relevant information be included, directly violated by omitting refusal data and equipment failure information.
Capability
Engineer B Scope-of-Work Non-Excuse Material Omission Recognition Failure II.3.a. requires complete reports regardless of contractual scope limitations, which Engineer B failed to recognize.
Capability
Engineer B Peer Technical Review Opportunity Preservation Failure II.3.a. requires complete reporting that enables independent review, which Engineer B's incomplete report undermined.
Capability
Engineer A Deposition Factual Completeness II.3.a. requires complete and truthful professional statements, which Engineer A demonstrated in deposition testimony.
Capability
Engineer A Geotechnical Consultant Independent Observer Completeness II.3.a. requires complete and objective professional reports and testimony, which Engineer A's consultant provided.
Capability
Engineer A Geotechnical Consultant Independent Observation Completeness II.3.a. requires complete and objective professional statements, which the independent consultant demonstrated.
Constraint
Engineer B Adversarial Expert Report Material Finding Disclosure Constraint. Litigation Context II.3.a. requires inclusion of all relevant and pertinent information in reports, directly creating the obligation Engineer B had to disclose all material findings in the expert report.
Constraint
Engineer A Deposition Factual Completeness Constraint. Geotechnical Report Pile Setup Testimony II.3.a. requires engineers to be objective and truthful in testimony and include all relevant information, directly governing Engineer A's deposition testimony obligations.
Constraint
Engineer B Adversarial Expert Report Material Finding Disclosure Wave Equation Equipment Failure II.3.a. requires all relevant and pertinent information be included in reports, directly creating the obligation to disclose wave equation results and equipment failure findings.
Constraint
Engineer B Written Report Completeness Constraint. Wave Equation Results and Equipment Failure II.3.a. directly mandates completeness in professional reports, requiring Engineer B to include wave equation analysis results and equipment failure facts.
Constraint
Engineer B Incomplete Risk Disclosure Constraint. Equipment Failure Non-Disclosure II.3.a. prohibits omission of relevant information from reports, directly creating the constraint against omitting the equipment failure material fact.
Constraint
Engineer B Written Report Completeness Wave Equation and Equipment Failure Omission II.3.a. requires all relevant and pertinent information in reports, directly establishing the completeness obligation violated by omitting wave equation and equipment failure data.
Constraint
Engineer B Adversarial Circumstance Non-Justification Selective Data Use Instance II.3.a. requires objectivity and completeness in reports regardless of context, directly prohibiting selective data use in adversarial circumstances.
Constraint
Engineer B Expert Report Peer Review Opportunity Foreclosure Language II.3.a. requires truthful and complete reporting, which supports drafting reports in a manner that does not foreclose independent review of the findings.
Constraint
Engineer B Adversarial Client Disservice Through Selective Reporting Municipality II.3.a. requires complete and truthful professional reports, directly creating the obligation to produce accurate reports that genuinely serve the client.
Constraint
Engineer B Incomplete Circumstantial Knowledge Adverse Pile Conclusions Without Full Record Review II.3.a. requires inclusion of all relevant information, directly prohibiting adverse conclusions drawn without reviewing all pertinent records.
Constraint
Engineer B Scope-of-Work Non-Exculpation Material Evidence Omission Pile Records Constraint Instance II.3.a. requires completeness in professional reports and cannot be overridden by contractual scope limitations when material information exists.
Constraint
Engineer B Intentional Information Disregard Constraint. Pile Driving Records Wave Equation II.3.a. requires all relevant and pertinent information be included, directly prohibiting intentional disregard of pile driving records when forming conclusions.
Constraint
Engineer B Intentional Information Disregard Pile Driving Records Constraint Instance II.3.a. mandates inclusion of all relevant information in reports, directly prohibiting selective omission of pile driving records from adverse conclusions.

Engineers may express publicly technical opinions that are founded upon knowledge of the facts and competence in the subject matter.

Applies To (31)
Role
Municipality Expert Witness Engineer The municipality's expert witnesses expressed public technical opinions during mediation about pile driving records, which must be founded on knowledge of facts and competence in the subject matter.
Role
Engineer A Geotechnical Consultant Independent Observer Engineer A's geotechnical consultant testified about dynamic test equipment failure and test results, requiring that such technical opinions be founded on knowledge and competence.
Principle
Available Evidence Consultation Violated By Engineer B Ignoring On-Site Representatives This provision requires technical opinions to be founded on knowledge of the facts, which Engineer B violated by not consulting available on-site representatives.
Principle
Incomplete Situational Knowledge Restraint Violated By Engineer B Adverse Conclusions Without Full Record Review This provision requires technical opinions to be based on competence and knowledge of facts, violated when Engineer B drew conclusions without reviewing pile driving records.
Principle
Available Evidence Consultation Obligation Violated by Engineer B This provision requires opinions to be founded on knowledge of the facts, directly violated by Engineer B's failure to consult available evidence sources.
Principle
Methodological Consistency Violated By Engineer B Using Vibratory Hammer This provision requires technical opinions to be competently founded, which is undermined by Engineer B using a methodologically inconsistent test approach.
Obligation
Engineer B Fact-Grounded Technical Opinion Pile Adequacy Conclusions II.3.b. requires technical opinions to be founded upon knowledge of the facts, directly applying to the obligation to base pile adequacy conclusions on all established facts.
Obligation
Engineer B Fact-Grounded Technical Opinion Obligation Violated II.3.b. requires technical opinions to be grounded in facts and competence, directly matching the obligation to express pile adequacy opinions only on complete factual basis.
Obligation
Engineer B Incomplete Knowledge Restraint Adverse Conclusions Without Full Record Review II.3.b. requires opinions to be founded upon knowledge of the facts, directly supporting the obligation to refrain from adverse conclusions without reviewing all records.
Obligation
Engineer B Available Evidence Consultation On-Site Representatives II.3.b. requires technical opinions to be based on knowledge of the facts, supporting the obligation to consult available evidence before issuing adverse conclusions.
Obligation
Engineer B Available Evidence Consultation Pile Driving Records Failure II.3.b. requires opinions to be founded on knowledge of facts, directly applying to the obligation to consult all reasonably available evidence including pile driving records.
Obligation
Engineer B Fact-Gathering Diligence Failure On-Site Representative II.3.b. requires technical opinions to be based on knowledge of the facts, directly supporting the obligation to gather facts from on-site representatives before concluding.
State
Engineer B Report Selective Omission of Pile Driving Records and Equipment Failure Engineer B's technical opinion on pile adequacy was not fully founded on all available facts, undermining the competence requirement for public technical opinions.
State
Engineer A Geotechnical Consultant Contradicting Engineer B's Test Findings The contradiction between Engineer A's consultant and Engineer B's findings raises questions about whether Engineer B's expressed opinion was fully grounded in the known facts.
State
Engineer B Compromised Test Condition Replication. Equipment Failure Issuing conclusions based on a test program with equipment failure means the technical opinion was not fully founded on sound and complete competence in the subject matter.
Resource
Wave-Equation-Pile-Analysis-Methodology-Instance This provision requires that technical opinions be founded on competence and knowledge of facts, including proper application of accepted methodology like wave equation analysis.
Resource
Engineer-B-Concluding-Report-Pile-Case This provision applies because Engineer B's public technical conclusions in the report must be founded on full knowledge of the facts and subject matter competence.
Resource
Conflicting-Expert-Report-Standard-Pile-Case This provision governs Engineer B's obligation to ensure that contradictory technical opinions expressed are founded on complete knowledge and competence.
Resource
Conflicting Expert Report Standard - Adversarial Pile Driving Dispute This provision applies because Engineer B expressed technical opinions challenging Engineer A's conclusions and must base those opinions on full factual competence.
Action
Contradictory Post-Report Explanations Public or professional technical opinions expressed post-report must be founded on knowledge of facts, which contradictory explanations undermine.
Event
Expert Testimony on Pile Failures Expert testimony on pile failures must be founded upon knowledge of the facts and competence in the subject matter.
Capability
Engineer B Pile Foundation Adequacy Evaluation II.3.b. requires technical opinions be founded on knowledge and competence, which Engineer B violated by rendering opinions without full analysis.
Capability
Engineer B Incomplete Knowledge Restraint Adverse Conclusions Failure II.3.b. requires that public technical opinions be founded on knowledge of facts, violated when Engineer B drew adverse conclusions without reviewing pile driving records.
Capability
Engineer B Pile Foundation Adequacy Evaluation Competence Failure II.3.b. requires competence in subject matter before expressing technical opinions, which Engineer B lacked by omitting wave equation analysis.
Capability
Engineer B Adverse Technical Opinion Evidence Consultation Failure II.3.b. requires technical opinions be founded on knowledge of facts, violated by failing to consult available evidence before rendering adverse opinions.
Capability
Engineer B Wave Equation Analysis Application Failure II.3.b. requires technical opinions be grounded in competent analysis, violated by omitting wave equation analysis before concluding on pile adequacy.
Constraint
Engineer B Fact-Grounded Opinion Constraint. Pile Adequacy Adverse Conclusions II.3.b. requires that publicly expressed technical opinions be founded on knowledge of the facts, directly creating the obligation to base adverse pile adequacy opinions on established facts.
Constraint
Engineer B Fact-Grounded Technical Opinion Pile Adequacy Without Full Evidence Base II.3.b. requires technical opinions to be grounded in knowledge of facts and competence, directly constraining Engineer B from issuing adverse opinions without a full evidence base.
Constraint
Engineer B Available Evidence Consultation Constraint. On-Site Representatives and Contractors II.3.b. requires opinions to be founded on knowledge of the facts, directly requiring consultation of available evidence sources before issuing adverse conclusions.
Constraint
Engineer B Fact-Gathering Diligence Failure Contractor Workers On-Site Representatives II.3.b. requires technical opinions to be based on knowledge of facts, directly creating the diligence obligation to gather facts from on-site representatives and contractors.
Constraint
Engineer B Incomplete Circumstantial Knowledge Adverse Pile Conclusions Without Full Record Review II.3.b. requires opinions to be founded on knowledge of the facts, directly prohibiting adverse conclusions formed without reviewing all available records.

Engineers shall issue no statements, criticisms, or arguments on technical matters that are inspired or paid for by interested parties, unless they have prefaced their comments by explicitly identifying the interested parties on whose behalf they are speaking, and by revealing the existence of any interest the engineers may have in the matters.

Applies To (26)
Role
Engineer B Adversarial Litigation Testing Supervisor Engineer B was retained and paid by the municipality in an adversarial dispute context, requiring explicit identification of the interested party on whose behalf comments were made.
Role
Municipality Expert Witness Engineer Expert witnesses were retained and paid by the municipality as an interested party in litigation, requiring disclosure of that relationship when issuing technical statements.
Principle
Adversarial Context Non-Exemption from Professional Standards Applied to Engineer B This provision addresses obligations when engineers speak on behalf of interested parties, directly relevant to Engineer B acting for the municipality in adversarial litigation.
Principle
Faithful Agent Obligation Invoked By Municipality Retaining Engineer B This provision requires disclosure of interested parties, relevant to Engineer B's role as agent of the municipality in a dispute.
Principle
Adversarial Engagement Objectivity Obligation Invoked Against Engineer B This provision governs statements made on behalf of interested parties, applicable to Engineer B producing a report for the municipality in litigation.
Obligation
Engineer B Adversarial Context Report Completeness Litigation II.3.c. requires engineers to identify interested parties when issuing technical statements on their behalf, applying to Engineer B's role retained by the municipality in litigation.
Obligation
Engineer B Artfully Misleading Scope-of-Work Explanation II.3.c. prohibits statements inspired by interested parties without disclosure, applying to Engineer B's misleading explanations made in the context of representing the municipality.
Obligation
Engineer B Adversarial Context Report Completeness Non-Selectivity Violation II.3.c. requires disclosure of interested party relationships when issuing technical statements, directly relevant to Engineer B's selective reporting on behalf of the municipality.
State
Engineer B Client-Aligned Advocacy Displacing Objective Reporting Engineer B's report appeared to serve the municipality's interests without explicitly identifying that the municipality was the paying interested party.
State
Engineer B Adversarial Engagement Without Coordination with Engineer A Engineer B issued technical conclusions on behalf of the municipality without disclosing the interested party relationship that shaped the evaluation.
State
Municipality vs Engineer A Adversarial Proceeding Fact Polarization In an adversarial proceeding where Engineer B was retained by one party, the obligation to disclose the interested party sponsoring the technical statements was directly applicable.
State
Engineer B Adversarial Expert Engagement Without Peer Coordination Engineer B's evaluation conducted solely on behalf of the municipality without disclosure of that interest violated the requirement to identify the interested party behind technical statements.
Resource
Conflicting-Expert-Report-Standard-Pile-Case This provision governs Engineer B's obligation to disclose that the municipality retained and paid for the report when issuing statements contradicting Engineer A.
Resource
Conflicting Expert Report Standard - Adversarial Pile Driving Dispute This provision applies because Engineer B was retained by an interested party and must explicitly identify that party when issuing technical criticisms.
Resource
Engineer-B-Concluding-Report-Pile-Case This provision requires Engineer B to disclose the municipality's interest when the report was inspired and paid for by that interested party.
Action
Municipality Retains Engineer B Engineer B must disclose any interest or the identity of the retaining party when issuing technical statements on behalf of the municipality.
Action
Selective Omission in Report If the report omissions were influenced by the retaining interested party, the engineer must disclose that relationship per this provision.
Event
Expert Testimony on Pile Failures If the expert testimony was paid for by an interested party in the lawsuit, the engineer must identify that party and any personal interest.
Event
Contractor Lawsuit Filed Technical statements or arguments made in the context of the lawsuit must disclose if they are inspired or paid for by an interested party.
Capability
Engineer B Facts Versus Adversarial Interests Distinction Failure II.3.c. requires disclosure of interested parties when opinions are paid for by them, directly relevant to Engineer B conflating adversarial interests with technical facts.
Capability
Engineer B Adversarial Context Non-Justification Recognition Failure II.3.c. requires engineers to identify interested parties when statements are inspired by them, violated when Engineer B allowed adversarial context to shape selective reporting.
Capability
Engineer B Litigation Context Intentional Evidence Disregard II.3.c. prohibits statements inspired by interested parties without disclosure, relevant to Engineer B disregarding evidence in a litigation context on behalf of a client.
Capability
Engineer B Client Disservice Through Selective Reporting Failure II.3.c. requires disclosure when reports are paid for by interested parties, relevant to Engineer B producing a selectively adverse report serving client litigation interests.
Constraint
Engineer B Adversarial Expert Report Material Finding Disclosure Constraint. Litigation Context II.3.c. prohibits statements inspired by interested parties without disclosure, directly relating to Engineer B's obligation to be transparent about the municipality's adversarial interest when issuing the expert report.
Constraint
Engineer B Retained Expert Impugning Engineer A Prohibition Instance II.3.c. prohibits technically framed arguments paid for by interested parties without disclosure, directly relating to the prohibition on producing a report that serves only to impugn Engineer A on behalf of the municipality.
Constraint
Engineer B Adversarial Client Disservice Through Selective Reporting Municipality II.3.c. addresses the risk of reports being shaped by interested party influence, directly relating to the constraint that Engineer B not allow the municipality's adversarial interest to drive selective reporting.
Section III. Professional Obligations 3 91 entities

Engineers shall advise their clients or employers when they believe a project will not be successful.

Applies To (15)
Role
Engineer B Municipality-Retained Litigation Testing Engineer Engineer B had a duty to advise the municipality client if the test pile driving results indicated the project or design would not be successful, rather than omitting such findings.
Principle
Client Disservice Through Incomplete Reporting Invoked Against Engineer B This provision requires engineers to advise clients when a project will not be successful, and Engineer B's incomplete reporting disserved the municipality's actual interests.
Principle
Faithful Agent Obligation Invoked By Municipality Retaining Engineer B This provision requires honest advisement to clients, relevant to Engineer B's obligation as the municipality's retained engineer to provide complete findings.
State
Engineer B Adversarial Engagement Without Coordination with Engineer A Engineer B had an obligation to advise the municipality client if the investigation findings were inconclusive or if the project outcome was uncertain rather than presenting a one-sided conclusion.
State
Engineer B Compromised Test Condition Replication. Equipment Failure When the test equipment failed and compromised the program, Engineer B should have advised the municipality client that the test results may not be reliable.
Resource
Engineer-Notification-Right-Pile-Case This provision relates to Engineer B's failure to contact Engineer A, which would have been a means of advising relevant parties about concerns with the project outcome.
Action
90-Pile Foundation Design If the engineer believed the foundation design would not be successful, this provision required advising the client accordingly.
Action
Vibratory Hammer Substitution Decision If the hammer substitution was likely to compromise the project, the engineer was obligated to advise the client of that risk.
Action
Inconsistent Pile Depth Decision Inconsistent pile depths suggesting potential project failure should have been communicated to the client as a warning of project risk.
Event
Piles Driven to Refusal The engineer should have advised the client if driving piles to refusal indicated the project would not proceed successfully as planned.
Event
Dynamic Test Equipment Failure The engineer should have advised the client that equipment failure compromised the ability to verify pile capacity successfully.
Capability
Engineer B Faithful Agent Municipality Report Completeness III.1.b. requires advising clients when projects will not be successful, relevant to Engineer B's failure to provide complete information to the municipality client.
Capability
Engineer B Client Disservice Through Selective Reporting Failure III.1.b. requires honest advisement to clients, violated when Engineer B's selective reporting actually disserved the municipality's interests.
Capability
Engineer B Adverse Evidence Consultation Failure III.1.b. requires engineers to advise clients accurately, which requires consulting all available evidence before rendering conclusions.
Constraint
Engineer B Adversarial Client Disservice Through Selective Reporting Municipality III.1.b. requires engineers to advise clients when a project will not be successful, directly relating to Engineer B's obligation to provide the municipality with complete and accurate findings rather than selectively favorable reporting.

Engineers shall acknowledge their errors and shall not distort or alter the facts.

Applies To (44)
Role
Engineer B Municipality-Retained Litigation Testing Engineer Engineer B distorted the factual record by omitting material facts such as equipment failure and piles driven to refusal from the official report.
Role
Engineer B Adversarial Litigation Testing Supervisor Engineer B's omission of critical facts from the report constitutes an alteration or distortion of the facts in violation of this provision.
Principle
Honesty Principle Violated By Engineer B Contradictory Explanations This provision requires engineers not to distort or alter facts, directly violated by Engineer B's contradictory and shifting explanations.
Principle
Objectivity Principle Violated by Engineer B Selective Data Use This provision prohibits distorting facts, which Engineer B effectively did by selectively omitting data that contradicted his conclusions.
Principle
Adversarial Objectivity Violated By Engineer B Omitting Wave Equation Results This provision requires acknowledgment of errors and prohibits distortion of facts, violated by Engineer B omitting material wave equation findings.
Principle
Scope-of-Work Defense Invoked By Engineer B to Justify Ignoring Pile Driving Records This provision requires not distorting facts, and Engineer B's contradictory scope-of-work defense constitutes a distortion of the factual basis for omissions.
Principle
Professional Accountability Invoked For Engineer B Report Deficiencies This provision requires engineers to acknowledge errors, directly invoking professional accountability for Engineer B's report deficiencies.
Obligation
Engineer B Intentional Information Disregard Pile Driving Records III.1.a. prohibits distorting or altering facts, directly applying to the obligation to refrain from intentionally disregarding pile driving records when forming conclusions.
Obligation
Engineer B Artfully Misleading Scope-of-Work Explanation III.1.a. requires engineers not to distort facts, directly applying to the obligation to refrain from making artfully misleading statements about omitting pile driving records.
Obligation
Engineer B Contradictory Explanation Non-Issuance Scope vs Disbelief III.1.a. requires acknowledgment of errors and prohibits distorting facts, directly applying to the obligation to provide consistent non-contradictory explanations.
Obligation
Engineer B Contradictory Professional Explanation Scope vs Disbelief III.1.a. prohibits distorting or altering facts, directly applying to the obligation to refrain from issuing contradictory explanations for omitting pile driving records.
Obligation
Engineer B Scope-of-Work Non-Excuse Pile Driving Records III.1.a. prohibits distorting facts, directly applying to the obligation to refrain from using scope-of-work as a false justification for omitting material evidence.
Obligation
Engineer B Scope-of-Work Non-Excuse Material Evidence Omission Pile Records III.1.a. prohibits distorting or altering facts, directly applying to the obligation not to invoke scope-of-work as justification for omitting material pile driving records.
Obligation
Engineer A Deposition Factual Completeness Geotechnical Report Testimony III.1.a. requires engineers not to distort or alter facts, directly applying to Engineer A's obligation to testify completely and accurately about the geotechnical report.
Obligation
Engineer A Geotechnical Consultant Independent Observer Testimony Completeness III.1.a. requires acknowledgment of errors and prohibits distorting facts, directly applying to the obligation to provide complete and objective testimony about all material observations.
State
Engineer B Contradictory Explanations for Ignoring Pile Driving Records Engineer B's shifting post-report explanations for not consulting pile driving records constitute distortion or alteration of the facts surrounding the investigation.
State
Engineer B Report Selective Omission of Pile Driving Records and Equipment Failure Omitting known facts about equipment failure and pile driving records from the report amounts to distorting the factual record.
State
Engineer B Selective Information Omission in Pile Driving Report Selectively omitting material facts from the submitted report directly violates the obligation not to distort or alter the facts.
State
Mediation Proceeding Transparency Obligations During mediation testimony, engineers must acknowledge errors and not distort facts, making this provision directly applicable to both engineers' conduct.
State
Engineer B Compromised Test Condition Replication. Equipment Failure Failing to acknowledge the equipment failure that compromised the test conditions represents a failure to acknowledge a material error in the testing process.
Resource
Engineer-B-Concluding-Report-Pile-Case This provision applies because Engineer B's omissions in the report constitute distortion or alteration of facts by excluding material findings.
Resource
Professional-Report-Integrity-Standard-Pile-Case This provision directly supports the standard requiring Engineer B not to distort facts by omitting the equipment failure and wave equation results.
Resource
Professional Report Integrity Standard - Pile Driving Test Report This provision is applied to Engineer B's failure to acknowledge material facts including equipment failure in the pile driving test report.
Resource
Pile-Driving-Records-Dock-Project This provision requires that facts contained in the pile driving records not be distorted or omitted from the engineering report.
Resource
Wave-Equation-Pile-Analysis-Methodology-Instance This provision requires Engineer B to acknowledge the wave equation results rather than omitting them, as omission constitutes distortion of technical facts.
Resource
Geotechnical-Firm-Report-Pile-Setup This provision requires that the geotechnical report establishing pile setup design basis not be ignored or distorted in Engineer B's conclusions.
Action
Selective Omission in Report Selectively omitting facts from a report constitutes distorting or altering the facts, which this provision explicitly prohibits.
Action
Contradictory Post-Report Explanations Providing contradictory explanations after the report distorts the factual record, violating the requirement not to alter the facts.
Action
Inconsistent Pile Depth Decision Failing to acknowledge or accurately represent inconsistent pile depth outcomes distorts the factual record of the project.
Action
Vibratory Hammer Substitution Decision Not acknowledging the substitution decision and its implications in reporting constitutes distortion of the facts.
Action
Pre-Count Hammer Drop Decision Concealing or misrepresenting the pre-count hammer drop decision distorts the factual basis of the engineering report.
Event
Geotechnical Report Strength-Gain Anticipation The engineer must not distort or omit facts regarding anticipated strength-gain in the geotechnical report.
Event
Dynamic Test Equipment Failure The engineer must acknowledge and not distort the fact that dynamic test equipment failed during testing.
Event
30-Day Strength Gain Confirmed The confirmed strength-gain data must not be altered or withheld from the report.
Capability
Engineer B Contradictory Explanation Issuance III.1.a. requires engineers not to distort or alter facts, violated by Engineer B issuing contradictory explanations that distorted the reason for omissions.
Capability
Engineer B Contradictory Professional Explanation Non-Issuance Failure III.1.a. requires acknowledgment of errors and no distortion of facts, directly violated by Engineer B's shifting contradictory explanations.
Capability
Engineer B Artfully Misleading Scope Explanation Recognition III.1.a. prohibits distorting facts, and Engineer B's sequential contradictory explanations constituted an artful distortion of the true reason for omissions.
Capability
Engineer B Selective Information Omission Recognition Failure III.1.a. requires not omitting material facts, directly violated by Engineer B's selective omission of refusal data and equipment failure.
Capability
Engineer B Scope-of-Work Non-Excuse Recognition Failure III.1.a. requires acknowledgment of errors rather than distortion, violated when Engineer B used scope-of-work as a false justification for omissions.
Constraint
Engineer A Deposition Factual Completeness Constraint. Geotechnical Report Pile Setup Testimony III.1.a. requires engineers not to distort or alter the facts, directly governing Engineer A's obligation to testify accurately and completely about the geotechnical report.
Constraint
Engineer B Contradictory Professional Justification Constraint. Scope vs. Disbelief III.1.a. prohibits distorting facts, directly applying to Engineer B's prohibition against offering mutually inconsistent justifications that misrepresent the true reason for omitting pile driving records.
Constraint
Engineer B Contradictory Professional Justification Scope vs Disbelief Constraint Instance III.1.a. requires acknowledgment of errors and prohibits distortion of facts, directly prohibiting Engineer B from offering contradictory explanations for the omission of pile driving records.
Constraint
Engineer B Intentional Information Disregard Constraint. Pile Driving Records Wave Equation III.1.a. prohibits distorting or altering facts, directly applying to Engineer B's intentional disregard of pile driving records when forming adverse conclusions.
Constraint
Engineer B Intentional Information Disregard Pile Driving Records Constraint Instance III.1.a. prohibits distortion or alteration of facts, directly prohibiting Engineer B from selectively omitting pile driving records to support adverse conclusions.

Engineers shall avoid the use of statements containing a material misrepresentation of fact or omitting a material fact.

Applies To (32)
Role
Engineer B Municipality-Retained Litigation Testing Engineer Engineer B issued a report omitting material facts about equipment failure and pile performance, directly violating the prohibition on statements that omit material facts.
Role
Engineer B Adversarial Litigation Testing Supervisor The report produced by Engineer B contained material omissions regarding the test pile driving program, constituting a statement omitting material facts.
Principle
Completeness Violated By Engineer B Omitting Equipment Failure This provision prohibits omitting material facts, directly violated by Engineer B's omission of the dynamic test equipment failure from the report.
Principle
Omission Materiality Threshold Crossed By Engineer B Wave Equation Omission This provision explicitly prohibits omitting material facts, and the wave equation results constituted a material fact whose omission crossed this threshold.
Principle
Adversarial Objectivity Violated By Engineer B Omitting Wave Equation Results This provision prohibits statements omitting material facts, directly applicable to Engineer B's report omitting the wave equation analysis results.
Principle
Prohibition on Reputation Injury Implicated By Engineer B Report Against Engineer A This provision prohibits material misrepresentation or omission of material facts, which Engineer B's selective reporting effectively used to injure Engineer A's reputation.
Principle
Objectivity Principle Violated By Engineer B Selective Reporting This provision prohibits omitting material facts from statements, directly violated by Engineer B reporting only skin friction results while omitting wave equation findings.
Principle
Methodological Consistency Obligation Implicated in Pile Driving Test Program This provision prohibits omitting material facts, and the methodological departure from original conditions was a material fact omitted from Engineer B's reporting.
Principle
Scope-of-Work Limitation as Incomplete Ethical Defense Invoked for Engineer B Report This provision's prohibition on omitting material facts cannot be circumvented by a contractual scope-of-work limitation, making such a defense ethically incomplete.
State
Engineer B Report Selective Omission of Pile Driving Records and Equipment Failure The report contained material omissions of pile driving records and equipment failure, constituting statements that omitted material facts.
State
Engineer B Selective Information Omission in Pile Driving Report The pile driving test report submitted to the municipality omitted material facts, directly violating the prohibition on statements that omit material facts.
State
Engineer B Contradictory Explanations for Ignoring Pile Driving Records Contradictory post-report explanations for ignoring records suggest the original report contained or was accompanied by misrepresentations of material fact.
State
Engineer B Available Witness Non-Consultation. Contractor and Workers Failing to consult available witnesses and omitting their potential testimony from the report resulted in a report omitting material facts.
State
Engineer B Client-Aligned Advocacy Displacing Objective Reporting Preparing a report aligned with the client's adversarial interests rather than objective findings risks producing statements that omit or misrepresent material facts.
State
Engineer B Failure to Consult Available On-Site Representatives Not consulting on-site representatives led to a report that omitted material facts that those representatives could have provided.
State
Engineer B Compromised Test Condition Replication. Equipment Failure Omitting the equipment failure from the report constitutes a statement omitting a material fact about the validity of the test conditions.
Resource
Engineer-B-Concluding-Report-Pile-Case This provision directly applies because the report omitted material facts including wave equation results and equipment failure, constituting a materially misleading statement.
Resource
Professional-Report-Integrity-Standard-Pile-Case This provision governs the same obligation this resource represents, prohibiting statements that omit material facts such as equipment failure and wave equation findings.
Resource
Professional Report Integrity Standard - Pile Driving Test Report This provision is directly applied to evaluate whether Engineer B's report omitted material facts in violation of ethical standards.
Resource
NSPE Code of Ethics - Complete Reporting Obligation This provision is part of the governing ethical authority prohibiting omission of material facts, which is the core obligation this resource references.
Resource
Wave-Equation-Pile-Analysis-Methodology-Instance This provision applies because omitting wave equation results that showed piles met strength requirements constitutes omission of a material fact.
Resource
Pile-Driving-Records-Dock-Project This provision applies because failing to fully account for pile driving records in the report constitutes omission of material technical facts.
Resource
Conflicting Expert Report Standard - Adversarial Pile Driving Dispute This provision applies because Engineer B's contradictory report must not omit material facts that would undermine or qualify its conclusions.
Action
Selective Omission in Report This provision directly prohibits statements that omit a material fact, which is the core nature of selective omission in the report.
Action
Contradictory Post-Report Explanations Contradictory explanations may contain material misrepresentations of fact, which this provision explicitly prohibits.
Action
Vibratory Hammer Substitution Decision Omitting or misrepresenting the hammer substitution decision in statements constitutes omission of a material fact under this provision.
Action
Pre-Count Hammer Drop Decision Failing to disclose the pre-count hammer drop decision in reports or statements omits a material fact relevant to the foundation analysis.
Action
Inconsistent Pile Depth Decision Omitting inconsistent pile depth outcomes from reports or statements constitutes omission of a material fact prohibited by this provision.
Event
Geotechnical Report Strength-Gain Anticipation Omitting anticipated strength-gain information from the geotechnical report constitutes omission of a material fact.
Event
Expert Testimony on Pile Failures Expert testimony must not misrepresent or omit material facts regarding the pile failures.
Event
Dynamic Test Equipment Failure Failing to disclose the equipment failure in statements or reports omits a material fact relevant to pile capacity conclusions.
Event
30-Day Strength Gain Confirmed Omitting confirmed strength-gain results from reports or statements constitutes omission of a material fact.
Cross-Case Connections
View Extraction
Implicit Similar Cases 10 Similarity Network

Cases sharing ontology classes or structural similarity. These connections arise from constrained extraction against a shared vocabulary.

Component Similarity 52% Facts Similarity 48% Discussion Similarity 66% Provision Overlap 75% Outcome Alignment 100% Tag Overlap 38%
Shared provisions: II.3.a, III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 60% Facts Similarity 60% Discussion Similarity 71% Provision Overlap 38% Outcome Alignment 100% Tag Overlap 62%
Shared provisions: II.3.a, III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 52% Facts Similarity 57% Discussion Similarity 46% Provision Overlap 33% Outcome Alignment 100% Tag Overlap 44%
Shared provisions: III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 50% Facts Similarity 44% Discussion Similarity 54% Provision Overlap 40% Outcome Alignment 100% Tag Overlap 33%
Shared provisions: III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 56% Facts Similarity 54% Discussion Similarity 51% Provision Overlap 20% Outcome Alignment 100% Tag Overlap 36%
Shared provisions: III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 46% Facts Similarity 45% Discussion Similarity 56% Provision Overlap 33% Outcome Alignment 100% Tag Overlap 36%
Shared provisions: II.3.a, III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 49% Facts Similarity 40% Discussion Similarity 55% Provision Overlap 29% Outcome Alignment 100% Tag Overlap 33%
Shared provisions: III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 51% Facts Similarity 35% Discussion Similarity 48% Provision Overlap 25% Outcome Alignment 100% Tag Overlap 33%
Shared provisions: III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 47% Facts Similarity 33% Discussion Similarity 39% Provision Overlap 33% Outcome Alignment 100% Tag Overlap 20%
Shared provisions: II.3.a, III.1.a, III.3.a Same outcome True View Synthesis
Component Similarity 56% Facts Similarity 56% Discussion Similarity 52% Provision Overlap 8% Outcome Alignment 100% Tag Overlap 33%
Shared provisions: III.1.a Same outcome True View Synthesis
Questions & Conclusions
View Extraction
Each question is shown with its corresponding conclusion(s). Board questions are expanded by default.
Decisions & Arguments
View Extraction
Causal-Normative Links 10
Fulfills None
Violates
  • Engineer B Objective Complete Report Equipment Failure Omission
  • Engineer B Objective Complete Report Wave Equation Omission
  • Engineer B Objective and Complete Reporting Wave Equation Omission
  • Adversarial Context Report Completeness and Non-Selectivity Obligation
  • Engineer B Adversarial Context Report Completeness Litigation
  • Engineer B Adversarial Context Report Completeness Non-Selectivity Violation
  • Client Disservice Through Selective Reporting Non-Commission Obligation
  • Engineer B Client Disservice Through Selective Reporting Municipality
  • Engineer B Faithful Agent Municipality Report Completeness
  • Engineer B Faithful Agent Obligation Violated by Selective Reporting
  • Scope-of-Work Non-Excuse for Material Evidence Omission Obligation
  • Engineer B Scope-of-Work Non-Excuse Pile Driving Records
  • Engineer B Scope-of-Work Non-Excuse Material Evidence Omission Pile Records
  • Engineer B Adversarial Circumstance Non-Justification Selective Data Use
  • Engineer B Peer Technical Review Opportunity Foreclosure Report Language
  • Engineer B Intentional Information Disregard Pile Driving Records
Fulfills
  • Engineer B Fact-Grounded Technical Opinion Pile Adequacy Conclusions
  • Fact-Gathering Diligence Obligation
Violates None
Fulfills
  • Engineer A Deposition Factual Completeness Geotechnical Report Testimony
  • Engineer A Geotechnical Consultant Independent Observer Testimony Completeness
Violates None
Fulfills
  • Engineer B Faithful Agent Municipality Report Completeness
  • Engineer B Adversarial Context Report Completeness Litigation
Violates
  • Peer Technical Review Opportunity Preservation Obligation
  • Engineer B Peer Technical Review Opportunity Foreclosure Report Language
Fulfills
  • Engineer A Geotechnical Consultant Independent Observer Testimony Completeness
  • Engineer A Deposition Factual Completeness Geotechnical Report Testimony
  • Peer Technical Review Opportunity Preservation Obligation
Violates None
Fulfills None
Violates
  • Comparative Testing Methodological Fidelity Obligation
  • Engineer B Comparative Testing Methodological Fidelity Vibratory Hammer
  • Engineer B Objective Complete Report Equipment Failure Omission
  • Engineer B Adversarial Context Report Completeness Non-Selectivity Violation
  • Engineer B Fact-Grounded Technical Opinion Obligation Violated
  • Engineer B Incomplete Knowledge Restraint Adverse Conclusions Without Full Record Review
Fulfills None
Violates
  • Comparative Testing Methodological Fidelity Obligation
  • Engineer B Comparative Testing Methodological Fidelity Vibratory Hammer
  • Engineer B Objective Complete Report Equipment Failure Omission
  • Engineer B Fact-Grounded Technical Opinion Pile Adequacy Conclusions
  • Engineer B Incomplete Knowledge Restraint Adverse Conclusions Without Full Record Review
Fulfills None
Violates
  • Comparative Testing Methodological Fidelity Obligation
  • Engineer B Comparative Testing Methodological Fidelity Vibratory Hammer
  • Engineer B Objective Complete Report Equipment Failure Omission
  • Engineer B Objective and Complete Reporting Wave Equation Omission
  • Engineer B Fact-Grounded Technical Opinion Pile Adequacy Conclusions
  • Engineer B Adversarial Context Report Completeness Non-Selectivity Violation
Fulfills None
Violates
  • Available Evidence Consultation Before Adverse Technical Opinion Obligation
  • Fact-Gathering Diligence Obligation
  • Engineer B Available Evidence Consultation On-Site Representatives
  • Engineer B Fact-Gathering Diligence Failure On-Site Representative
  • Engineer B Available Evidence Consultation Pile Driving Records Failure
  • Engineer B Incomplete Knowledge Restraint Adverse Conclusions Without Full Record Review
  • Engineer B Fact-Grounded Technical Opinion Obligation Violated
  • Peer Technical Review Opportunity Preservation Obligation
Fulfills None
Violates
  • Contradictory Professional Explanation Non-Issuance Obligation
  • Engineer B Contradictory Explanation Non-Issuance Scope vs Disbelief
  • Engineer B Contradictory Professional Explanation Scope vs Disbelief
  • Engineer B Artfully Misleading Scope-of-Work Explanation
  • Engineer B Fact-Grounded Technical Opinion Obligation Violated
  • Engineer B Adversarial Context Report Completeness Non-Selectivity Violation
Decision Points 6

When dynamic test equipment fails during a comparative pile driving program that forms the evidentiary basis for adverse conclusions about another engineer's work, what disclosure obligation does the reporting engineer bear?

Options:
Prominently Disclose Failure And Qualify Conclusions Board's choice Disclose the equipment failure prominently in the report, explain its potential effect on data reliability, and qualify the adverse conclusions accordingly so that readers can independently assess the weight of the test results
Note Failure In Appendix Without Elevating It Note the equipment failure in the technical appendix as a procedural observation without elevating it to the conclusions section, on the basis that the engineer's professional judgment determined it did not affect the structural findings
Omit Failure As Outside Contractual Scope Omit the equipment failure from the report on the grounds that the contractual scope of work defined deliverables as test pile results rather than test program conditions, and that the failure was a field contingency managed during execution
Toulmin Summary:
Warrants II.3.a III.3.a

The Adversarial Context Report Completeness and Non-Selectivity Obligation requires Engineer B to include all material findings regardless of adversarial context. The Client Disservice Through Selective Reporting Non-Commission Obligation recognizes that omitting the failure also harms the municipality by undermining the report's credibility when exposed. The Faithful Agent Obligation to the municipality requires complete and accurate reporting that serves the municipality's legitimate, not merely tactical, interests.

Rebuttals

Uncertainty arises if the equipment failure could be characterized as immaterial to the ultimate pile adequacy conclusions: i.e., if Engineer B could demonstrate that the failure did not affect the specific blow-count or penetration data on which his conclusions rested. Additionally, if the scope-of-work agreement with the municipality explicitly limited reporting to test results rather than test program conditions, Engineer B might argue the failure was outside the contractual deliverable. However, the Board rejected both defenses: the failure was foundationally material because it undermined the reliability of the entire test data set, and the scope-of-work limitation cannot override the Code's categorical prohibition on material omissions that create false impressions.

Grounds

Dynamic test equipment failed during Engineer B's test pile driving program. Engineer B drew adverse conclusions about the adequacy of 19 piles based on that test program. The equipment failure was not disclosed anywhere in the concluding report. Engineer A's geotechnical consultant later testified about the failure in mediation proceedings.

Before issuing adverse professional conclusions about another engineer's pile design in a litigation context, what fact-gathering obligations does the retained expert bear with respect to available on-site witnesses and primary records?

Options:
Consult On-Site Representatives Before Finalizing Board's choice Contact Engineer A's on-site representatives and the contractor's supervisors and workers before finalizing the report, document their accounts of original pile driving conditions, and incorporate or address that testimony in the conclusions
Limit Sources To Provided Documentation Only Limit fact-gathering to the test pile program and the pile driving records provided by the municipality, on the basis that the adversarial litigation context makes direct contact with Engineer A's representatives legally and professionally inappropriate without coordinating through counsel
Disclose Gaps And Qualify Adverse Conclusions Disclose in the report that on-site representatives and construction workers were not consulted, identify the specific factual questions that consultation would have addressed, and qualify the adverse conclusions to reflect the evidentiary gap created by the absence of firsthand witness testimony
Toulmin Summary:
Warrants II.3.b II.3.c

The Available Evidence Consultation Before Adverse Technical Opinion Obligation requires consulting all reasonably available evidence sources before publishing conclusions adverse to another engineer's professional standing. The Fact-Gathering Diligence Obligation requires diligent inquiry from available witnesses before drawing and publishing professional conclusions. Code Section II.3.b requires that technical opinions be founded upon knowledge of the facts, an obligation that is procedural and cannot be satisfied by selectively assembling a subset of available facts.

Rebuttals

Uncertainty is created by whether the adversarial litigation context genuinely transforms the professional consultation obligation into an impermissible ex parte communication, if Engineer A's representatives were represented by counsel in the underlying lawsuit, direct contact might have been legally constrained. Additionally, if Engineer B's scope of work explicitly excluded stakeholder consultation, the contractual framing might appear to relieve him of the obligation. The Board rejected both defenses: the adversarial context heightens rather than relaxes the objectivity standard, and the scope-of-work limitation cannot waive the Code's requirement that adverse opinions be fact-grounded.

Grounds

Engineer B was retained by the municipality to supervise test pile driving and evaluate the adequacy of 19 disputed piles. Engineer A's on-site representatives were available and possessed material knowledge about the pile driving records and original installation conditions. Contractor supervisors and workers who were present during original construction were also available. Engineer B consulted none of these parties before issuing adverse conclusions. Engineer B advanced a specific theory about pile venting through closure plates without asking the workers who installed those closure plates.

When pile driving records and accepted wave equation analysis directly contradict an adverse conclusion about pile adequacy, what obligation does the reporting engineer bear to disclose that contradictory evidence in the report?

Options:
Analyze Records And Report Refusal Findings Board's choice Apply wave equation analysis to the available pile driving records, disclose that the 19 questioned piles were driven to essential refusal at capacities several multiples above design requirements, and reconcile that finding with the depth-based test program results in the report's conclusions
Disclose Records And Recommend Further Analysis Disclose the existence of the pile driving records and the refusal data in the report, note that wave equation analysis was outside the contracted scope, and recommend that the municipality commission a supplemental analysis before relying on the test program conclusions for litigation purposes
Exclude Records While Noting Their Existence Exclude the pile driving records from the report on the basis that their reliability is professionally questionable, but disclose in the report that the records exist, that they were considered and found suspect, and that the specific basis for that professional judgment is the engineer's assessment of their internal consistency
Toulmin Summary:
Warrants II.3.a III.3.a III.3 (completeness requirement)

The Completeness and Non-Selectivity Obligation, invoked via the Code requirement that engineers 'shall include all relevant and pertinent information', required disclosure of the refusal data and wave equation results. The Client Disservice Through Incomplete Reporting Prohibition recognizes that omitting this evidence deprived the municipality of a rational basis for evaluating the opposing party's position. The Scope-of-Work Non-Excuse for Material Evidence Omission Obligation establishes that a contractual scope limitation cannot justify omitting evidence that directly contradicts the report's central finding.

Rebuttals

Uncertainty is created by whether Engineer B had a professionally defensible basis for discrediting the driving records as unreliable: if the records were genuinely suspect, their exclusion might be methodologically defensible provided that judgment was disclosed. Additionally, if Engineer B's depth-based analysis methodology was the accepted standard for the test program and wave equation analysis was outside the contracted scope, the omission might appear to fall within legitimate scope boundaries. The Board rejected both defenses: Engineer B's post-report acknowledgment that the records 'look suspicious' confirmed he was aware of them and made a conscious choice to exclude them, collapsing the scope defense; and the materiality of the wave equation results, directly exculpatory of Engineer A's design, crossed the disclosure threshold regardless of scope.

Grounds

The 19 piles Engineer B concluded were inadequate had, according to pile driving records, been driven to essential refusal. Accepted wave equation calculations applied to those records would have indicated load capacity several multiples above design requirements. Engineer B did not disclose this in his report. Post-report, Engineer B offered two contradictory explanations: first that the records were outside his scope of work, then that he simply did not believe them. The geotechnical report had anticipated strength gain in the soil, and 30-day strength gain was subsequently confirmed.

When a comparative test pile driving program uses materially different equipment and procedures than the original installation, what obligation does the supervising engineer bear to ensure methodological fidelity or disclose departures that affect the validity of the comparison?

Options:
Replicate Original Conditions Or Disclose Departures Board's choice Replicate the original pile driving conditions, including hammer type, penetration depth requirements, and blow-count recording protocols, in the test program, or disclose all material departures in the report and qualify the adverse conclusions to reflect the limits of comparability
Disclose Substitutions As Indicative Results Proceed with the available equipment and field conditions, disclose the vibratory hammer substitution and depth variations in the report's methodology section, and present the test results as indicative rather than definitive comparators pending a fully replicated test program
Proceed Without Disclosing Method Departures Apply professional judgment that the vibratory hammer and modified depth protocol are sufficiently equivalent for the purposes of the evaluation, proceed without disclosure of the departures, and issue conclusions based on the test results as if they were directly comparable to the original installation
Toulmin Summary:
Warrants II.3.a II.3.b

The Comparative Testing Methodological Fidelity Obligation requires use of the same hammer type, penetration depth requirements, and blow-count recording protocols as the original program, or disclosure of material deviations. The Methodological Consistency Obligation in Comparative Testing requires that testing conditions be sufficiently consistent with original conditions to permit valid comparison. Issuing definitive adverse conclusions from data the engineer knew or should have known was not a valid basis for comparison constitutes a violation of Code Section II.3.a's requirement that professional reports be objective and truthful.

Rebuttals

Uncertainty arises because if the vibratory hammer substitution and depth inconsistency were disclosed in the report with appropriate methodological caveats, acknowledging non-comparability, the ethical violation would be substantially mitigated, as the engineer would have preserved the reader's ability to properly weight the results. Additionally, if the vibratory hammer was the only equipment available and the municipality's scope of work did not specify hammer type, the substitution might appear to be a field-level engineering judgment rather than an ethical departure. The Board concluded that the absence of any disclosure of these departures, combined with the issuance of unqualified adverse conclusions, transformed what might have been a defensible methodological choice into an ethical violation.

Grounds

Engineer B supervised a test pile driving program intended to evaluate whether piles would gain sufficient strength to meet design requirements. The test program used a vibratory hammer rather than the hammer type used in original pile installation. Pre-count hammer drops were allowed before blow counts were recorded, which Engineer A's geotechnical consultant testified would have broken the pile bond and undervalued skin friction. Penetration depth requirements were not consistently replicated. Engineer B drew definitive adverse conclusions from the test results without disclosing any of these methodological departures.

When an engineer is queried about the basis for excluding material evidence from an adverse professional report, what honesty and non-distortion obligations govern the engineer's account of those investigative choices?

Options:
Provide Single Transparent Exclusion Rationale Board's choice Provide a single, coherent, and transparent account of why the pile driving records were excluded, either acknowledging they were outside the contracted scope and that this limitation should have been disclosed in the report, or acknowledging they were reviewed and found unreliable and explaining the specific professional basis for that judgment
Maintain Scope Explanation With Added Clarification Maintain the scope-of-work explanation as the primary justification, acknowledge that the records were brought to the engineer's attention during the engagement, and clarify that the scope limitation was a contractual boundary that the municipality and engineer agreed upon before the work commenced
Maintain Disbelief Explanation With Technical Basis Maintain the disbelief explanation as the primary justification, provide the specific technical or documentary basis for finding the records unreliable, and acknowledge that this professional judgment should have been disclosed in the report rather than left unstated
Toulmin Summary:
Warrants III.1.a II.3.c

Code Section III.1.a prohibits engineers from distorting or altering the facts. The issuance of contradictory professional justifications for a consequential investigative choice, one that affected adverse conclusions about another engineer's work, constitutes a distortion of the factual basis of the report's methodology. The honesty obligation extends beyond the report document to how an engineer accounts for professional choices when queried. The Technical Facts Non-Adversarial Character principle establishes that factual findings and the engineer's treatment of them are not legitimately subject to adversarial framing or post-hoc reconstruction.

Rebuttals

The virtue ethics analysis becomes uncertain under the rebuttal condition that contradictory explanations might reflect genuine epistemic evolution rather than strategic inconsistency, meaning that if Engineer B initially believed the records were outside his scope and later, upon reflection, concluded he had in fact reviewed them and found them unreliable, the contradiction might represent honest recollection rather than deliberate distortion. However, the Board concluded that the two positions are structurally incompatible, not merely sequentially different, and that an engineer of professional competence would recognize and acknowledge the incompatibility rather than advancing both without reconciliation.

Grounds

After issuing his report, Engineer B was queried about why the pile driving records were excluded. He first stated the records were not within his scope of work. He subsequently stated he simply did not believe the records. These two explanations are mutually exclusive: the scope explanation implies the records were never evaluated; the disbelief explanation implies they were evaluated and consciously rejected. Engineer B offered both without acknowledging the contradiction or explaining which was true. The disbelief explanation inadvertently confirmed that the records were known and considered, collapsing the scope-of-work defense.

When a retained litigation expert's obligation to serve the client's interests appears to conflict with the professional obligation to produce a complete and non-selective report, how should the engineer resolve that tension, and does the adversarial context of the engagement alter the applicable standard?

Options:
Report All Material Findings Without Selection Board's choice Produce a complete and non-selective report that includes all material findings, wave equation results, equipment failure, pile driving refusal data, regardless of whether those findings are adverse to the municipality's litigation position, serving the municipality's legitimate interest in a professionally defensible and credible technical assessment
Report Scoped Results And Recommend Supplement Produce a report focused on the test pile program results within the contracted scope, disclose the scope limitation prominently, and recommend that the municipality commission a supplemental analysis addressing the pile driving records and wave equation methodology before relying on the report for litigation purposes
Decline Engagement Due To Conflict Concerns Decline the engagement on the grounds that the adversarial litigation context and the municipality's defined scope create irreconcilable pressure to produce a client-favorable rather than objectively complete report, and advise the municipality to retain an expert whose scope of work is defined broadly enough to permit complete and objective reporting
Toulmin Summary:
Warrants II.3.a II.3.c III.3.a

The Faithful Agent Obligation required Engineer B to serve the municipality's legitimate interests. The Adversarial Context Report Completeness and Non-Selectivity Obligation required Engineer B to produce a complete and non-selective report regardless of the adversarial context. The Client Disservice Through Incomplete Reporting Prohibition establishes that selective omissions ultimately harm the client by undermining the report's credibility when exposed. Code Section II.3.c prohibits technical statements inspired by the interest of other parties, a provision most directly applicable in adversarial contexts where the temptation to accommodate client preferences is greatest.

Rebuttals

Uncertainty is created by the question of whether the Faithful Agent Obligation in a litigation context is bounded by the Completeness Obligation, that is, whether 'faithful service' to a client can legitimately include producing a report that emphasizes findings favorable to the client while omitting findings favorable to the opposing party, on the theory that the adversarial process itself will surface the omitted evidence through opposing expert testimony. Under this view, Engineer B's role was analogous to that of an advocate, and the completeness obligation would be satisfied at the system level rather than the individual report level. The Board rejected this view entirely: the NSPE Code does not contain an adversarial-context exception to the completeness obligation, and the engineer's professional obligations run to the profession and the public, not merely to the client's tactical interests.

Grounds

The municipality retained Engineer B to supervise test pile driving and evaluate pile adequacy in the context of a contractor lawsuit. Engineer B's report omitted the equipment failure, the wave equation results, the pile driving refusal data, and was produced without consulting Engineer A's representatives or on-site witnesses. The report's adverse conclusions were later contradicted by Engineer A's geotechnical consultant's testimony in mediation. The municipality's litigation position was ultimately undermined when the omissions were exposed. The case settled in mediation.

15 sequenced 10 actions 7 events
Action (volitional) Event (occurrence) Associated decision points
DP3
Engineer B issued a report concluding that 19 piles were inadequate without disc...
Analyze Records And Report Refusal Findi... Disclose Records And Recommend Further A... Exclude Records While Noting Their Exist...
Full argument
DP1
Engineer B omitted from his report the fact that dynamic test equipment failed d...
Prominently Disclose Failure And Qualify... Note Failure In Appendix Without Elevati... Omit Failure As Outside Contractual Scop...
Full argument
DP5
Engineer B offered two mutually exclusive post-report explanations for why the p...
Provide Single Transparent Exclusion Rat... Maintain Scope Explanation With Added Cl... Maintain Disbelief Explanation With Tech...
Full argument
DP6
Engineer B was retained by the municipality in an adversarial litigation context...
Report All Material Findings Without Sel... Report Scoped Results And Recommend Supp... Decline Engagement Due To Conflict Conce...
Full argument
DP4
Engineer B designed and supervised a comparative test pile driving program using...
Replicate Original Conditions Or Disclos... Disclose Substitutions As Indicative Res... Proceed Without Disclosing Method Depart...
Full argument
4 30-Day Strength Gain Confirmed 30 days after test pile driving
5 90-Pile Foundation Design Initial design phase, prior to construction
6 Mediation Settlement Agreement Post-construction, during mediation proceedings
7 Municipality Retains Engineer B During or immediately following mediation, prior to test pile driving
DP2
Engineer B issued adverse conclusions about the adequacy of 19 piles without con...
Consult On-Site Representatives Before F... Limit Sources To Provided Documentation ... Disclose Gaps And Qualify Adverse Conclu...
Full argument
9 Inconsistent Pile Depth Decision During test pile driving program
10 Decision to Exclude Stakeholder Consultation During report preparation, following test pile driving
11 Contradictory Post-Report Explanations After report issuance, in response to Engineer A's post-report inquiry
12 Contractor Lawsuit Filed Post-construction, prior to mediation
13 Mediation Settlement Reached During mediation proceedings, prior to pile testing phase
14 Expert Testimony on Pile Failures During mediation proceedings
15 Piles Driven to Refusal During original construction and/or test pile driving phase
Causal Flow
  • 90-Pile_Foundation_Design Mediation Settlement Agreement
  • Mediation Settlement Agreement Municipality Retains Engineer B
  • Municipality Retains Engineer B Engineer A Retains Independent Observer
  • Engineer A Retains Independent Observer Vibratory Hammer Substitution Decision
  • Vibratory Hammer Substitution Decision Pre-Count_Hammer_Drop_Decision
  • Pre-Count_Hammer_Drop_Decision Inconsistent Pile Depth Decision
  • Inconsistent Pile Depth Decision Decision to Exclude Stakeholder Consultation
  • Decision to Exclude Stakeholder Consultation Selective Omission in Report
  • Selective Omission in Report Contradictory_Post-Report_Explanations
  • Contradictory_Post-Report_Explanations Contractor Lawsuit Filed
Opening Context
View Extraction

You are Engineer B, a geotechnical engineer retained by a municipality to supervise a test pile driving program designed to determine whether piles installed in a dock foundation would gain sufficient load-bearing strength over time to meet the original design requirements. The program was commissioned in the context of active litigation involving Engineer A, the dock's designer, and a contractor dispute that had already resulted in a $300,000 mediated settlement. During the test program, the dynamic testing equipment failed, and the test piles were not driven to the same depth of penetration as the original piles, meaning the conditions required for plug formation were not replicated. A vibratory hammer was used rather than the equipment used in the original installation. You are now preparing your report on the test results, which will be submitted to the municipality and used as evidence in the ongoing dispute. The choices you make about what to include, what to consult, and how to represent the testing conditions will define the professional and ethical standing of your work.

From the perspective of Engineer A Dock Foundation Design Engineer
Characters (8)
protagonist

An independent geotechnical expert retained by the design engineer to observe the same test pile driving supervised by Engineer B, who documented significant procedural and equipment irregularities that fundamentally undermined the validity of Engineer B's conclusions.

Motivations:
  • To provide an objective, technically rigorous counter-narrative that would expose methodological flaws in the municipality's testing process and thereby protect Engineer A's professional reputation and legal position.
  • To protect the integrity of the original design, vindicate professional judgment, and limit personal and financial liability exposure arising from the contractor dispute.
stakeholder

A licensed engineer retained during active litigation to supervise test pile driving and produce an evaluative report, who produced findings of pile deficiency while omitting critical contradictory data including equipment failure, wave equation analysis, and available on-site consultation.

Motivations:
  • Likely influenced by client expectations and litigation context to produce findings favorable to the municipality, resulting in selective reporting that prioritized the client's legal position over complete and objective technical disclosure.
  • To minimize financial liability to the contractor by obtaining engineering reports and expert testimony that would support the adequacy of the original pile foundation design.
stakeholder

Retained by the municipality to supervise test pile driving and produce a report evaluating whether piles met design safety factors. Produced a report finding 19 of 90 piles deficient, but omitted material data: failed to report equipment failure, omitted wave equation analysis showing piles at essential refusal, failed to consult Engineer A's on-site representatives, and gave contradictory explanations for scope limitations. Central figure in the ethical analysis.

decision-maker

Retained by Engineer A to independently observe the test pile driving supervised by Engineer B. Testified that dynamic test equipment failed, that test piles were not driven to required penetration depth, that a vibratory hammer was used (not used in original driving), and that pre-test hammer drops would have broken pile bond and undervalued skin friction — thereby challenging the validity of Engineer B's test results.

stakeholder

Expert witness(es) retained by the municipality during mediation proceedings who testified that pile driving records indicated many piles did not meet driving resistance sufficient to satisfy load-carrying requirements of the design calculations.

decision-maker

Retained by the municipality to supervise the test pile driving program; produced a report omitting material facts (equipment failure, piles driven to refusal) that selectively supported the municipality's adversarial position, failed to communicate with Engineer A's on-site representative, and failed to inquire from contractors and workers — constituting a failure of fact-gathering diligence and an egregious denial of professional duties.

stakeholder

Party to an adversarial dispute with Engineer A over settlement cost sharing; arranged and funded the test pile driving program; retained Engineer B; ultimately harmed by Engineer B's incomplete report which misdirected conclusions.

decision-maker

Engineer A's representative present on-site during the test pile driving program; Engineer B failed to communicate with this individual, constituting a diligence failure in fact-gathering.

Ethical Tensions (9)

Tension between Adversarial Context Report Completeness and Non-Selectivity Obligation and Scope-of-Work Limitation as Incomplete Ethical Defense

Obligation Vs Constraint
Affects: Engineer B Objective Complete Report Equipment Failure Omission

Tension between Available Evidence Consultation Before Adverse Technical Opinion Obligation and Fact-Gathering Diligence Obligation

Obligation Vs Constraint
Affects: Engineer B Available Evidence Consultation On-Site Representatives

Tension between Adversarial Context Report Completeness and Non-Selectivity Obligation and Scope-of-Work Non-Excuse for Material Evidence Omission Obligation

Obligation Vs Constraint
Affects: Engineer B Objective Complete Report Wave Equation Omission

Tension between Comparative Testing Methodological Fidelity Obligation and Methodological Consistency Obligation in Comparative Testing

Obligation Vs Constraint
Affects: Engineer B Comparative Testing Methodological Fidelity Vibratory Hammer

Tension between Client Disservice Through Selective Reporting Non-Commission Obligation and Technical Facts Non-Adversarial Character Invoked in Pile Driving Report Case

Obligation Vs Constraint
Affects: Engineer B Adversarial Circumstance Non-Justification Selective Data Use

Tension between Adversarial Context Report Completeness and Non-Selectivity Obligation and Client Disservice Through Incomplete Reporting Prohibition

Obligation Vs Constraint
Affects: Engineer B Faithful Agent Municipality Report Completeness

Engineer B is retained by the Municipality as a litigation testing engineer, creating a structural pull toward serving the client's adversarial litigation interests. However, the constraint requiring disclosure of all material findings in an expert report — regardless of adversarial context — directly conflicts with the temptation to act as a faithful agent by suppressing findings unfavorable to the Municipality. Fulfilling the faithful-agent duty as the client construes it (winning the case) would require omitting wave equation results and equipment failure data; fulfilling the disclosure constraint means potentially harming the client's litigation position. This is a genuine dilemma because both duties are professionally grounded yet point in opposite directions.

Obligation Vs Constraint
Affects: Engineer B Municipality-Retained Litigation Testing Engineer Municipality Litigation Testing Client Municipality Expert Witness Engineer
Moral Intensity (Jones 1991):
Magnitude: high Probability: high immediate direct concentrated

Engineer B is obligated not to intentionally disregard pile driving records when forming professional opinions, yet the constraint requiring that adverse conclusions about pile adequacy be grounded in available facts creates a direct collision. If Engineer B consults the pile driving records and wave equation analyses, those facts may undermine or contradict the adverse conclusions the Municipality's litigation position requires. The tension is genuine: honoring the fact-grounded opinion constraint means incorporating evidence that may exonerate the opposing party, while the intentional-disregard obligation flags that selectively ignoring that same evidence is an independent ethical violation. Either path carries professional and ethical cost.

Obligation Vs Constraint
Affects: Engineer B Municipality-Retained Litigation Testing Engineer Adversarial Litigation Testing Supervisor Engineer Municipality Expert Witness Engineer
Moral Intensity (Jones 1991):
Magnitude: high Probability: high immediate direct concentrated

Engineer B offered two mutually inconsistent justifications for omitting pile driving records: (1) they were outside the scope of work, and (2) he personally disbelieved them. The obligation that scope-of-work cannot excuse material evidence omission strips away the first defense, while the constraint prohibiting contradictory professional justifications strips away the second — and flags that invoking both simultaneously is itself an ethical violation. The tension is that Engineer B cannot simultaneously claim he was not required to consider the records AND that he considered them but rejected them; each justification undermines the other, yet abandoning both leaves the omission entirely unjustified. This exposes a deeper dilemma between professional self-protection and honest accounting of one's reasoning.

Obligation Vs Constraint
Affects: Engineer B Municipality-Retained Litigation Testing Engineer Municipality Litigation Testing Client Adversarial Litigation Testing Supervisor Engineer
Moral Intensity (Jones 1991):
Magnitude: high Probability: high immediate direct concentrated
Opening States (10)
Contradictory Scope Justification State Available Witness Non-Consultation State Compromised Test Condition Replication State Adversarial Expert Engagement Without Peer Coordination State Engineer B Report Selective Omission of Pile Driving Records and Equipment Failure Engineer B Failure to Consult Available On-Site Representatives Test Pile Program Compromised Conditions Engineer B Contradictory Explanations for Ignoring Pile Driving Records Engineer B Adversarial Engagement Without Coordination with Engineer A Engineer A Geotechnical Consultant Contradicting Engineer B's Test Findings
Key Takeaways
  • Engineers serving as expert witnesses in adversarial proceedings cannot use scope-of-work limitations as justification for omitting material evidence that would affect the integrity of their technical conclusions.
  • When issuing adverse technical opinions, engineers bear an affirmative duty to consult all available evidence, including evidence of equipment malfunction that may undermine the reliability of their own findings.
  • Report completeness and non-selectivity obligations persist regardless of which party retained the engineer, meaning adversarial context does not license cherry-picking favorable data while suppressing unfavorable technical facts.